What is the objective of a sprint retrospective meeting?
- A . Improve the scrum process
- B . Review and prioritize the backlog
- C . Provide formal feedback to the project manager
- D . Define the stakeholder management approach
In SAP activate, what tool is used in the agile delivery approach during the realize phase.
- A . Product Increment
- B . Project plan
- C . Burndown chart
- D . Release plan
What information does the project team need before they can.
- A . Definition of done
- B . Available project resources
- C . Overall project schedule
- D . Test strategy
Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase? There are 2 correct answers to this question
- A . Kick-off workshop
- B . Integration prerequisites confirmation
- C . Fit-to-standard workshop
- D . Configuration definition
What is the Primary Purpose of the SAP Activate Methodology?
- A . To enable access to the SAP ecosystem
- B . To Provide the Sequence of actions in the project
- C . To provide end-to-end Application Lifecycle Management
- D . To manage solution documentation
Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 correct answers to this question
- A . Building blocks
- B . Configuration guides
- C . Scope items
- D . Business process scenarios
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 correct answers to this question
- A . Extraction of business units
- B . System consolidation
- C . Security migration
- D . Consolidation through online data replication
- E . System upgrade
What are some of the key characteristics of the implementation approach in SAP Activate methodology? There are 3 correct answers to this question.
- A . On premise only
- B . ActivaDelta-based
- C . Cloud ready
- D . Fixed scope
- E . Based on ready-to-use content
In which phase do you verify that the SAP best practices content meets the customer’s Business needs?
- A . Realize
- B . Deploy
- C . Prepare
- D . Explore
Which activity helps the Project Team add User Stories to the Product Backlog?
- A . Assessing project risks
- B . Preparing a project schedule
- C . Conducting the Solution Validation workshop
- D . Planning the User Acceptance Test