What is the primary function of the Starter System in the Fit-to-Standard workshops?
- A . To gather the customer’s detailed configuration requirements
- B . To provide a secondary sandbox that will be maintained by the customer post go-live
- C . To demonstrate SAP Best Practices
- D . To configure and test the solution in a sandbox
Which of the following will help you avoid modification of standard functionality in SAP S/4HANA cloud single edition? There are 3 correct answers to this question.
- A . Contract restrictions in SAP HANA enterprise cloud and SAP S/4HANA cloud single tenant edition
- B . The side-by-side extensibility option (such as SAP cloud platform)
- C . The 5 golden rules
- D . A developer key
What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate? Please choose the correct answer.
- A . Project Charter
- B . Project Documentation
- C . Knowledge transfer to end users
- D . Learning plan
What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question.
- A . Premium engagement ready
- B . On-premise only
- C . Fixed scope
- D . Validate solution
- E . Start with SAP Best Practices
What is the purpose of a firm-up sprint?
- A . To revise the release plan and sprint plan
- B . To demonstrate functionality from previous sprints
- C . To perform string test
- D . To run an end-to-end integration test
Which of the following can be used to navigate through the roadmap? There are 2 correct answers to this question.
- A . Deliverables
- B . Phases
- C . Tasks
- D . Workstreams
In which phase do you create "an ordered list of everything that is known to be needed in the Product?
- A . Realize
- B . Deploy
- C . Explore
- D . Prepare
Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation? There are 3 correct answers to this question.
- A . Adjusting custom code objects
- B . Implementing best practices
- C . Creating transnational data
- D . Changing master data
- E . Organizational structure
What tool do you use to configure an SAP Business Suite on-premise solution? Please choose the correct answer.
- A . ABAP Workbench
- B . SAP Implementation Guide
- C . Configuration Composer
- D . Expert Configuration
Which of the following are the benefits of SAP JAM? There are 2 correct answers to this question.
- A . User collaboration
- B . Reduced Recovery Time
- C . Easy to use
- D . Highly available