Question #1

Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer.

  • A . Navigate by assigned Delivery Mode
  • B . Navigate by RACI matrix accountability
  • C . Navigate by work stream
  • D . Navigate by Project Team Member Role

Reveal Solution Hide Solution

Correct Answer: C
Question #2

What are some characteristics of SAP S/4HANA Cloud?

  • A . SAP S/4HANA Cloud is single-tenant; meaning your service runs in a dedicated environment.
  • B . SAP S/4HANA Cloud is multi-tenant, meaning your service runs in a shared environment.
  • C . SAP S/4HANA Cloud includes quarterly innovation cycles.
  • D . SAP S/4HANA Cloud runs in an infrastructure with private, managed services for SAP solutions.
  • E . SAP S/4HANA Cloud provides additional functionality for customers that require broad extensions and deep configuration capabilities.

Reveal Solution Hide Solution

Correct Answer: B,C
Question #3

Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the correct answer.

  • A . Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
  • B . Relative estimate in ideal person days that reflects the best estimate provided by the project team
  • C . Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
  • D . Product Owner’s relative estimate of the effort that will be needed to implement the user story

Reveal Solution Hide Solution

Correct Answer: D
Question #4

How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 correct answers to this question.

  • A . Demo the SAP model company
  • B . User acceptance test
  • C . Solution demo for sprints
  • D . Solution review for waves

Reveal Solution Hide Solution

Correct Answer: C,D
Question #5

Which tools does SAP Activate provide to support Guided Configuration? There are 3 correct answers to this question.

  • A . Solution Builder
  • B . Expert Configuration
  • C . Self Service Configuration
  • D . SAP Solution Composer
  • E . Model Company

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #6

Which new role is introduced in the SAP activate methodology in a full scrum team?

  • A . Project manager
  • B . Application consultant
  • C . Product owner
  • D . System administrator

Reveal Solution Hide Solution

Correct Answer: C
Question #7

Which of the following is not correct about Fit/Gap Analysis? There are 2 correct answers to this question.

  • A . Prioritize delta requirement and gaps.
  • B . Drive towards adopting customers processes.
  • C . Minimize the needs for rework during realization.
  • D . Validate pre-activate and pre-assembled solution in the development system.

Reveal Solution Hide Solution

Correct Answer: B,D
Question #8

How would you describe the realise phase in the "new implementation of SAP S/4HANA" transition path?

  • A . Configure and adjust custom code
  • B . Configuration copy
  • C . Configure
  • D . Configure and develop

Reveal Solution Hide Solution

Correct Answer: A
Question #9

Which deliverable is specific to on-premise and NOT for the cloud? Please choose the correct answer.

  • A . Technical Design Solution
  • B . Knowledge Transfer
  • C . Adaptation Specification
  • D . Learning Needs Analysis

Reveal Solution Hide Solution

Correct Answer: B
Question #10

Which activity helps the project team to add the user stories to the product backlog? Please choose the correct answer.

  • A . Planning the User Acceptance Test
  • B . Preparing a Project Schedule
  • C . Conducting the Solution Validation
  • D . Assessing Project Risks

Reveal Solution Hide Solution

Correct Answer: C

Question #11

In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?

  • A . Deploy
  • B . Realize
  • C . Prepare
  • D . Explore

Reveal Solution Hide Solution

Correct Answer: B
Question #12

Which activities are critical for delivering Agile projects? There are 2 correct answers to this question.

  • A . Retrospective agenda creation
  • B . Sprint planning
  • C . Release planning
  • D . Blueprint scheduling

Reveal Solution Hide Solution

Correct Answer: B,C
Question #13

What do you do during an iterative approach to build a solution? Please choose the correct answer.

  • A . Build the solution module by module
  • B . Deliver a prototype of the solution
  • C . Provide a working solution only at the end of the release
  • D . Include frequent inspection check-points

Reveal Solution Hide Solution

Correct Answer: D
Question #14

Which of the following are available in the initial SAP Methodologies JAM Page? There are 2 correct answers to this question.

  • A . Task description
  • B . Accelerators
  • C . Summary
  • D . Roadmaps

Reveal Solution Hide Solution

Correct Answer: B,D
Question #15

What is the best transition scenario for a customer looking for some, but not full process redesign, and re-use of existing processes in some areas that still fit?

  • A . Selective Data Transition
  • B . New Implementation
  • C . System Conversion

Reveal Solution Hide Solution

Correct Answer: A
Question #16

In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the correct answer.

  • A . Supports cloud deployments
  • B . Supports only new implementations
  • C . Leverages iterative incremental build
  • D . Includes Fit/Gap analysis instead of Blueprint

Reveal Solution Hide Solution

Correct Answer: D
Question #17

What is the minimum number of quality gates mandated by the SAP Activate methodology? Please choose the correct answer.

  • A . 0
  • B . 3
  • C . 4
  • D . 5

Reveal Solution Hide Solution

Correct Answer: C
Question #18

Which accelerator can help you document the detailed design of solution extensions? Please choose the correct answer.

  • A . Change Request Template
  • B . Product Backlog Template
  • C . Sprint Backlog Template
  • D . RICEF Specification Template

Reveal Solution Hide Solution

Correct Answer: D
Question #19

Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 correct answers to this question.

  • A . Building blocks
  • B . Configuration guides
  • C . Business process scenarios
  • D . Scope items

Reveal Solution Hide Solution

Correct Answer: A,D
Question #20

How many change projects can be active at a time?

  • A . 3
  • B . 2
  • C . 4
  • D . 1

Reveal Solution Hide Solution

Correct Answer: D

Question #21

What is the purpose of the Solution Validation activity in the Explore phase? There are 3 correct answers to this question.

  • A . To verify technical installation
  • B . To identify gaps
  • C . To log additional scope items
  • D . To challenge changes to standard
  • E . To educate project participants

Reveal Solution Hide Solution

Correct Answer: B,C,D
Question #22

What are SCRUM of SCRUMS? Please choose the correct answer.

  • A . Alternative to regular SCRUM process for smaller teams
  • B . Integration meeting between the various project teams
  • C . Frequent inspection of code and configuration prior to quality gates
  • D . Mechanism for gathering and validating requirements

Reveal Solution Hide Solution

Correct Answer: B
Question #23

Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase? There are 2 correct answers to this question.

  • A . Kick-off workshop
  • B . Integration prerequisites confirmation
  • C . Fit-to-standard workshop
  • D . Configuration definition

Reveal Solution Hide Solution

Correct Answer: C,D
Question #24

In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question.

  • A . DEV
  • B . P-system
  • C . QAS
  • D . Starter system

Reveal Solution Hide Solution

Correct Answer: A,C
Question #25

What SAP middleware tool hosts the SAP Best Practices pre-delivered integration content and can be used for custom integration development?

  • A . SAP HANA Enterprise Cloud
  • B . SAP API Management
  • C . Process Integration
  • D . SAP Cloud Platform

Reveal Solution Hide Solution

Correct Answer: D
Question #26

Which new project roles are introduced with the SAP Activate Agile methodology? There are 2 correct answers to this question.

  • A . SCRUM Master
  • B . Product Owner
  • C . Integration Lead
  • D . Design Thinking Coach

Reveal Solution Hide Solution

Correct Answer: A,B
Question #27

What are some activities the project team will perform in executing project work during the Explore Phase?

  • A . Collect project data and report on progress and performance
  • B . Manage risks and implement risk response activities
  • C . Manage Background Jobs, Input and Output.
  • D . Deal with user authorization requests.
  • E . Establish and manage internal and external communications

Reveal Solution Hide Solution

Correct Answer: A,B,E
Question #28

What are some of the capabilities end users can utilize to adapt and change their launchpad home page according to the way they work?

  • A . Rearrange or move tiles within a group
  • B . Add any SAP Fiori apps to a group, regardless of role
  • C . Delete a predelivered group
  • D . Rename a predelivered tile
  • E . Add a new group

Reveal Solution Hide Solution

Correct Answer: A,D,E
Question #29

What are some extension item types can be transported from the Quality system to the Production system?

  • A . Form Templates
  • B . Custom Fields
  • C . Communication Arrangements
  • D . Master Data
  • E . Query Designer Report
  • F . Employee Data
  • G . Custom Business Logic

Reveal Solution Hide Solution

Correct Answer: A,B,E,G
Question #30

Which content is made available after you activate SAP Best Practices for a new financial implementation? There are 2 correct answers to this question.

  • A . Implementation Guide
  • B . Online help
  • C . Pre-configured business processes
  • D . Standard chart of accounts

Reveal Solution Hide Solution

Correct Answer: C,D

Question #31

What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 correct answers to this question.

  • A . Different sets of workstreams are used for these transition paths
  • B . Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
  • C . There are different roles in the application design and configuration workstream
  • D . SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option

Reveal Solution Hide Solution

Correct Answer: B,D
Question #32

What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 correct answers to this question.

  • A . Set Project policy, standards and oversight
  • B . Set business priorities, goals and objectives
  • C . Identify and resolve issues and risks
  • D . Perform status reporting and communication

Reveal Solution Hide Solution

Correct Answer: C,D
Question #33

Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 correct answers to this question.

  • A . System consolidation
  • B . System upgrade
  • C . Consolidation through online data replication
  • D . Extraction of business units
  • E . Security migration

Reveal Solution Hide Solution

Correct Answer: A,C,D
Question #34

Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question

  • A . Schedule kick-off workshop
  • B . Conduct Scope Validation
  • C . Confirm Integration prerequisites
  • D . Perform Fit/Gap Analysis

Reveal Solution Hide Solution

Correct Answer: B,D
Question #35

Which criterion does the Product Owner use to sequence the product backlog? Please choose the correct answer.

  • A . Resource availability
  • B . Complexity
  • C . Business priority
  • D . Relative effort

Reveal Solution Hide Solution

Correct Answer: C
Question #36

In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer.

  • A . Prepare
  • B . Explore
  • C . Realize
  • D . Deploy

Reveal Solution Hide Solution

Correct Answer: D
Question #37

Who determines the tasks that are required to complete the committed backlog items in a sprint? Please choose the correct answer.

  • A . Project Manager
  • B . Product Owner
  • C . Project Team
  • D . SCRUM Master

Reveal Solution Hide Solution

Correct Answer: C
Question #38

What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path. There are 2 correct option to this question.

  • A . There are different upgrade cycles
  • B . In the realize phase, custom code is adjusted rather than developed for system conversion
  • C . In the realize phase, data is converted and not migrated for system conversion
  • D . SSCUI’s are used in system conversion for configuring SAP S/4HANA through the manage Your solution app

Reveal Solution Hide Solution

Correct Answer: B,C
Question #39

Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 correct answers to this question.

  • A . SAP cloud appliance library
  • B . SAP App centre
  • C . Blu-ray disks
  • D . SAP Solution Builder tool

Reveal Solution Hide Solution

Correct Answer: A,C
Question #40

What are some goals of the Fit-to-Standard workshops?

  • A . To define the Integration and API List for the solution.
  • B . To review the SAP Best Practices in the starter system.
  • C . To identify relevant data migration objects.
  • D . To identify customer-defined configuration changes within the scope of the service.
  • E . To gather input for customer-defined customizations to the solution.

Reveal Solution Hide Solution

Correct Answer: B,D,E

Question #41

What is SAP Activate? Please choose the correct answer.

  • A . A step-by-step instruction on how to remove from SAP best practices to your custom solution
  • B . A methodology for each of the deployment modes (cloud, on-premise, hybrid)
  • C . A bundle of ASAP, SAP Launch, and Rapid Deployment Solutions
  • D . A combination of SAP best practices, methodology, and guided configuration

Reveal Solution Hide Solution

Correct Answer: D
Question #42

What are some responsibilities of the Configuration Expert project team role in an SAP S/4HANA Cloud implementation?

  • A . Manages interactions with the SAP Service Center
  • B . Serves as the central contact for SAP
  • C . Resolution of business process issues
  • D . Prepares and leads the Fit-to-Standard analysis process

Reveal Solution Hide Solution

Correct Answer: C,D
Question #43

Where can you find the Migration Object Template documentation?

  • A . SAP Support Portal
  • B . SAP Best Practices Explorer
  • C . SAP Roadmap Viewer accelerator
  • D . SAP Help Portal

Reveal Solution Hide Solution

Correct Answer: D
Question #44

Which of the following building blocks are part of the SAP S/4HANA platform? There are 2 correct answers to this question.

  • A . SAP Fiori UX
  • B . SAP HANA in-memory database
  • C . SAP Solution Manager
  • D . LOB Cloud Solution

Reveal Solution Hide Solution

Correct Answer: A,B
Question #45

In which tools can the project team across the SAP Activate Methodology content including accelerators? There are 2 correct answers to this question.

  • A . SAP Community Network
  • B . Roadmap Viewer
  • C . SAP Jam
  • D . SAP Service Marketplace

Reveal Solution Hide Solution

Correct Answer: B,C
Question #46

Which of the following statements about Scrum is correct? Please choose the correct answer.

  • A . Scrum Master defines and prioritizes features and gathers requirements.
  • B . In Scrum, the team is Self-organized, define all task necessary for all project life cycle.
  • C . In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
  • D . The three ceremonies are sprint planning, daily scrum, sprint review (retrospective).

Reveal Solution Hide Solution

Correct Answer: D
Question #47

What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the system conversion?

  • A . Simplification item check (Si-check)
  • B . Software update manager with database migration option
  • C . SAP code inspector
  • D . Software provisioning manager

Reveal Solution Hide Solution

Correct Answer: A
Question #48

How can organizations closely connect subsidiaries with headquarters to run end-to-end business scenarios?

  • A . With a cloud solution
  • B . With a 2-tier ERP solution
  • C . With a 4-tier ERP solution
  • D . With a fully functional ERP solution

Reveal Solution Hide Solution

Correct Answer: B
Question #49

What do you do during Sprint Execution? Please choose the correct answer.

  • A . End a sprint when the sprint backlog items are all complete
  • B . Measure the sprint progress with a percentage complete report
  • C . Hold a retrospective at the end of each week
  • D . Present status of selected user stories in the sprint scope on a scrumboard

Reveal Solution Hide Solution

Correct Answer: B
Question #50

In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer.

  • A . Deploy
  • B . Explore
  • C . Prepare
  • D . Realize

Reveal Solution Hide Solution

Correct Answer: C

Question #51

What is the primary function of the Starter System in the Fit-to-Standard workshops?

  • A . To gather the customer’s detailed configuration requirements
  • B . To provide a secondary sandbox that will be maintained by the customer post go-live
  • C . To demonstrate SAP Best Practices
  • D . To configure and test the solution in a sandbox

Reveal Solution Hide Solution

Correct Answer: C
Question #52

Which of the following will help you avoid modification of standard functionality in SAP S/4HANA cloud single edition? There are 3 correct answers to this question.

  • A . Contract restrictions in SAP HANA enterprise cloud and SAP S/4HANA cloud single tenant edition
  • B . The side-by-side extensibility option (such as SAP cloud platform)
  • C . The 5 golden rules
  • D . A developer key

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #53

What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate? Please choose the correct answer.

  • A . Project Charter
  • B . Project Documentation
  • C . Knowledge transfer to end users
  • D . Learning plan

Reveal Solution Hide Solution

Correct Answer: D
Question #54

What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question.

  • A . Premium engagement ready
  • B . On-premise only
  • C . Fixed scope
  • D . Validate solution
  • E . Start with SAP Best Practices

Reveal Solution Hide Solution

Correct Answer: A,D,E
Question #55

What is the purpose of a firm-up sprint?

  • A . To revise the release plan and sprint plan
  • B . To demonstrate functionality from previous sprints
  • C . To perform string test
  • D . To run an end-to-end integration test

Reveal Solution Hide Solution

Correct Answer: C
Question #56

Which of the following can be used to navigate through the roadmap? There are 2 correct answers to this question.

  • A . Deliverables
  • B . Phases
  • C . Tasks
  • D . Workstreams

Reveal Solution Hide Solution

Correct Answer: B,D
Question #57

In which phase do you create "an ordered list of everything that is known to be needed in the Product?

  • A . Realize
  • B . Deploy
  • C . Explore
  • D . Prepare

Reveal Solution Hide Solution

Correct Answer: A
Question #58

Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation? There are 3 correct answers to this question.

  • A . Adjusting custom code objects
  • B . Implementing best practices
  • C . Creating transnational data
  • D . Changing master data
  • E . Organizational structure

Reveal Solution Hide Solution

Correct Answer: C,D,E
Question #59

What tool do you use to configure an SAP Business Suite on-premise solution? Please choose the correct answer.

  • A . ABAP Workbench
  • B . SAP Implementation Guide
  • C . Configuration Composer
  • D . Expert Configuration

Reveal Solution Hide Solution

Correct Answer: B
Question #60

Which of the following are the benefits of SAP JAM? There are 2 correct answers to this question.

  • A . User collaboration
  • B . Reduced Recovery Time
  • C . Easy to use
  • D . Highly available

Reveal Solution Hide Solution

Correct Answer: A,C

Question #61

Where can you find the integration content? There are 3 correct answers to this question.

  • A . SAP cloud appliance library
  • B . SAP Solution manger
  • C . SAP API business hub
  • D . SAP Best practices explorer
  • E . Cloud integration automatic service

Reveal Solution Hide Solution

Correct Answer: A,C,D
Question #62

How can the project manager help to keep momentum in the project and help to keep the customer involved?

  • A . Leverage agile cycles to build and test the solution
  • B . Increase the number of Q-Gates
  • C . Add customer resources to the project to reduce the need for formal training
  • D . Walk through the solution processes with the stakeholders

Reveal Solution Hide Solution

Correct Answer: A,C
Question #63

Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.

What is the correct sequence of selected key deliverables across the project phases? Please choose the correct answer.

  • A . a) Code adjustment
    b) Detailed System Assessment
    c) Production Readiness Check
    d) Validation of Migration
  • B . a) Production Readiness Check
    b) Detailed system Assessment
    c) Code Adjustment
    d) Validation of Migration
  • C . a) Detailed system Assessment
    b) Code Adjustment
    c) Validation of Migration
    d) Production Readiness Check
  • D . a) Detailed system Assessment
    b) Production Readiness Check
    c) Code Adjustment
    d) Validation of Migration

Reveal Solution Hide Solution

Correct Answer: C
Question #64

What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-premise? Please choose the correct answer.

  • A . Key Deliverable
  • B . Scenario
  • C . Work Stream
  • D . Task

Reveal Solution Hide Solution

Correct Answer: A
Question #65

When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer.

  • A . During the daily SCRUM meeting
  • B . During the sprint retrospective
  • C . During the sprint review
  • D . During user acceptance testing

Reveal Solution Hide Solution

Correct Answer: C
Question #66

In SAP Activate, what replaces the detailed Blueprint from ASAP? Please choose the correct answer.

  • A . Business Process Mapping
  • B . Value Determination
  • C . Custom Extension management
  • D . Fit/Gap Workshops

Reveal Solution Hide Solution

Correct Answer: D
Question #67

In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the correct answer.

  • A . Realize
  • B . Deploy
  • C . Explore
  • D . Prepare

Reveal Solution Hide Solution

Correct Answer: C
Question #68

What does the side-by-side extensibility option mean?

  • A . Transfer reporting to BW/4HANA
  • B . Context-aware SAP S/4HANA extensions, focused on tight integration
  • C . Extensibility based on the SAP cloud platform and published APIs
  • D . Have two SAP S/4HANA instances-one for standard code, and another for customer developments

Reveal Solution Hide Solution

Correct Answer: C
Question #69

What is the most granular level of the methodology you can view in the SAP roadmap viewer?

  • A . Task
  • B . Deliverables
  • C . Scenario
  • D . Phase

Reveal Solution Hide Solution

Correct Answer: A
Question #70

Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 correct answers to this question.

  • A . User acceptance test-plan
  • B . Reporting functional specifications
  • C . Functional test scenarios
  • D . Functional specifications

Reveal Solution Hide Solution

Correct Answer: A,C