What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 correct answers to this question.
- A . Different sets of workstreams are used for these transition paths
- B . Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
- C . There are different roles in the application design and configuration workstream
- D . SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option
What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 correct answers to this question.
- A . Set Project policy, standards and oversight
- B . Set business priorities, goals and objectives
- C . Identify and resolve issues and risks
- D . Perform status reporting and communication
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 correct answers to this question.
- A . System consolidation
- B . System upgrade
- C . Consolidation through online data replication
- D . Extraction of business units
- E . Security migration
Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question
- A . Schedule kick-off workshop
- B . Conduct Scope Validation
- C . Confirm Integration prerequisites
- D . Perform Fit/Gap Analysis
Which criterion does the Product Owner use to sequence the product backlog? Please choose the correct answer.
- A . Resource availability
- B . Complexity
- C . Business priority
- D . Relative effort
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer.
- A . Prepare
- B . Explore
- C . Realize
- D . Deploy
Who determines the tasks that are required to complete the committed backlog items in a sprint? Please choose the correct answer.
- A . Project Manager
- B . Product Owner
- C . Project Team
- D . SCRUM Master
What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path. There are 2 correct option to this question.
- A . There are different upgrade cycles
- B . In the realize phase, custom code is adjusted rather than developed for system conversion
- C . In the realize phase, data is converted and not migrated for system conversion
- D . SSCUI’s are used in system conversion for configuring SAP S/4HANA through the manage Your solution app
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 correct answers to this question.
- A . SAP cloud appliance library
- B . SAP App centre
- C . Blu-ray disks
- D . SAP Solution Builder tool
What are some goals of the Fit-to-Standard workshops?
- A . To define the Integration and API List for the solution.
- B . To review the SAP Best Practices in the starter system.
- C . To identify relevant data migration objects.
- D . To identify customer-defined configuration changes within the scope of the service.
- E . To gather input for customer-defined customizations to the solution.