In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?
- A . Deploy
- B . Realize
- C . Prepare
- D . Explore
Which activities are critical for delivering Agile projects? There are 2 correct answers to this question.
- A . Retrospective agenda creation
- B . Sprint planning
- C . Release planning
- D . Blueprint scheduling
What do you do during an iterative approach to build a solution? Please choose the correct answer.
- A . Build the solution module by module
- B . Deliver a prototype of the solution
- C . Provide a working solution only at the end of the release
- D . Include frequent inspection check-points
Which of the following are available in the initial SAP Methodologies JAM Page? There are 2 correct answers to this question.
- A . Task description
- B . Accelerators
- C . Summary
- D . Roadmaps
What is the best transition scenario for a customer looking for some, but not full process redesign, and re-use of existing processes in some areas that still fit?
- A . Selective Data Transition
- B . New Implementation
- C . System Conversion
In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the correct answer.
- A . Supports cloud deployments
- B . Supports only new implementations
- C . Leverages iterative incremental build
- D . Includes Fit/Gap analysis instead of Blueprint
What is the minimum number of quality gates mandated by the SAP Activate methodology? Please choose the correct answer.
- A . 0
- B . 3
- C . 4
- D . 5
Which accelerator can help you document the detailed design of solution extensions? Please choose the correct answer.
- A . Change Request Template
- B . Product Backlog Template
- C . Sprint Backlog Template
- D . RICEF Specification Template
Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 correct answers to this question.
- A . Building blocks
- B . Configuration guides
- C . Business process scenarios