In which phase of the SAP Activate methodology does the team complete the Transformation Planning? Please choose the correct answer.

  • A . Deploy
  • B . Explore
  • C . Prepare
  • D . Realize

Reveal Solution Hide Solution

Correct Answer: D
Question #2

In which phase you execute the User Acceptance Test? Please choose the correct answer.

  • A . Build and Test
  • B . Deploy
  • C . Final Preparation
  • D . Realize

Reveal Solution Hide Solution

Correct Answer: D
Question #3

What is the purpose of the SAP Activate Methodology? Please choose the correct answer.

  • A . To enable access to the SAP ecosystem
  • B . To accelerate the initial implementation of SAP S/4HANA
  • C . To provide end-to-end integrated application lifecycle management
  • D . To manage project and solution documentation

Reveal Solution Hide Solution

Correct Answer: B
Question #4

Which component of SAP Activate offers customers a reference solution in the cloud for a quick start? Please choose the correct answer.

  • A . SAP Implementation Assistant
  • B . SAP Activate Methodology
  • C . Guided Configuration
  • D . SAP Best Practices

Reveal Solution Hide Solution

Correct Answer: D
Question #5

In Which phase does the Transition to Operations work stream start? Please choose the correct answer.

  • A . Explore
  • B . Realize
  • C . Deploy
  • D . Prepare

Reveal Solution Hide Solution

Correct Answer: C
Question #6

What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-premise? Please choose the correct answer.

  • A . Key Deliverable
  • B . Scenario
  • C . Work Stream
  • D . Task

Reveal Solution Hide Solution

Correct Answer: A
Question #7

Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase? There are 2 correct answers to this question.

  • A . Sprint Backlog Template
  • B . RICEF Specification Template
  • C . Solution Validation Workshop
  • D . Quality Gate Checklist

Reveal Solution Hide Solution

Correct Answer: B,C
Question #8

In which tools can the project team across the SAP Activate Methodology content including accelerators? There are 2 correct answers to this question.

  • A . SAP Community Network
  • B . Roadmap Viewer
  • C . SAP Jam
  • D . SAP Service Marketplace

Reveal Solution Hide Solution

Correct Answer: B,C
Question #9

Which of the following activities are part of the Deploy Phase of a Landscape Transformation journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question.

  • A . Solution Activation
  • B . Optimize software Change Control Management
  • C . Training delivery
  • D . Access organizational and production readiness

Reveal Solution Hide Solution

Correct Answer: C,D
Question #10

What is the best target environment for a System Conversion journey is as described in the SAP Activate methodology? Please choose the correct answer.

  • A . SAP Hybris
  • B . SAP S/4HANA Cloud Edition
  • C . SAP S/4HANA On-Premise Edition
  • D . Hybrid of SAP S/4HANA Cloud Edition and SAP S/4HANA On-Premise Edition

Reveal Solution Hide Solution

Correct Answer: C

Question #11

What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer.

  • A . Start with executable content
  • B . Limited involvement of business stakeholders
  • C . Waterfall approach
  • D . Design-based

Reveal Solution Hide Solution

Correct Answer: A
Question #12

Which of the following building blocks are part of the SAP S/4HANA platform? There are 2 correct answers to this question.

  • A . SAP Fiori UX
  • B . SAP HANA in-memory database
  • C . SAP Solution Manager
  • D . LOB Cloud Solution

Reveal Solution Hide Solution

Correct Answer: A,B
Question #13

What do you do during post cutover? Please choose the correct answer.

  • A . Setup Operational Support
  • B . Perform the Verification Session of the SAP Going Live Check
  • C . Perform Technical System Test
  • D . Conduct Organizational Readiness Check

Reveal Solution Hide Solution

Correct Answer: B
Question #14

In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the customer? Please choose the correct answer.

  • A . Explore
  • B . Deploy
  • C . Realize
  • D . Prepare

Reveal Solution Hide Solution

Correct Answer: A
Question #15

What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question.

  • A . Premium engagement ready
  • B . On-premise only
  • C . Fixed scope
  • D . Validate solution
  • E . Start with SAP Best Practices

Reveal Solution Hide Solution

Correct Answer: A,D,E
Question #16

According to the Definition of Done, which activity must be completed for each sprint? Please choose the correct answer.

  • A . End user training must be delivered
  • B . Solution must be built and configured in the development system (DEV)
  • C . Functionality must be tested in the Quality system (QAS)
  • D . Functionality must be released to the business

Reveal Solution Hide Solution

Correct Answer: B
Question #17

In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer.

  • A . Deploy
  • B . Explore
  • C . Prepare
  • D . Realize

Reveal Solution Hide Solution

Correct Answer: C
Question #18

What is the most granular level of the methodology you can view in the Roadmap Viewer? Please choose the correct answer.

  • A . Scenario
  • B . Task
  • C . Deliverables
  • D . Phase

Reveal Solution Hide Solution

Correct Answer: B
Question #19

What is SAP Activate? Please choose the correct answer.

  • A . A step-by-step instruction on how to remove from SAP best practices to your custom solution
  • B . A methodology for each of the deployment modes (cloud, on-premise, hybrid)
  • C . A bundle of ASAP, SAP Launch, and Rapid Deployment Solutions
  • D . A combination of SAP best practices, methodology, and guided configuration

Reveal Solution Hide Solution

Correct Answer: D
Question #20

What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition? Please choose the correct answer.

  • A . SAP Best Practices
  • B . Rapid prototyping
  • C . Project team training
  • D . Full project SCRUM

Reveal Solution Hide Solution

Correct Answer: A

Question #21

What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices? Please choose the correct answer.

  • A . Activate and apply SAP Best Practices content with the self-service configuration UI
  • B . Activate and apply SAP Best Practices with SAP Solution Manager
  • C . Apply SAP Best Practices with the Configure your Solution application
  • D . Assemble and apply SAP Best Practices to the system

Reveal Solution Hide Solution

Correct Answer: B
Question #22

What are the responsibilities of the Product Owner in release and sprint planning? There are 2 correct answers to this question.

  • A . Analyze the functional and technical dependencies between the user stories
  • B . Define objectives for each release
  • C . Prioritize backlog user stories by business priority
  • D . Estimate the backlog user stories

Reveal Solution Hide Solution

Correct Answer: B,C
Question #23

Which of the following content best outlines the scope of the Integration Test? Please choose the correct answer.

  • A . a. Prototype
  • B . Delta/gap solutions
  • C . Data flows with non-SAP application
  • D . a. Prototype
  • E . Delta configuration
  • F . Data flows between SAP solutions
  • G . a. Solution baseline
  • H . Delta/gap solutions
  • I . Data flows with non-SAP application
  • J . a. Solution baseline
  • K . Delta configuration
  • L . Data flows between SAP solutions

Reveal Solution Hide Solution

Correct Answer: C
Question #24

What are deliverables of the Application: Integration work stream in the prepare phase? There are 3 correct answers to this question.

  • A . Fit/Gap Analysis
  • B . Data Cleansing
  • C . Security Checks
  • D . Adaptation Specifications
  • E . Network Connectivity Checks

Reveal Solution Hide Solution

Correct Answer: C,D,E
Question #25

Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer.

  • A . Navigate by assigned Delivery Mode
  • B . Navigate by RACI matrix accountability
  • C . Navigate by work stream
  • D . Navigate by Project Team Member Role

Reveal Solution Hide Solution

Correct Answer: C