In which phase of the SAP Activate methodology does the team complete the Transformation Planning? Please choose the correct answer.
- A . Deploy
- B . Explore
- C . Prepare
- D . Realize
In which phase you execute the User Acceptance Test? Please choose the correct answer.
- A . Build and Test
- B . Deploy
- C . Final Preparation
- D . Realize
What is the purpose of the SAP Activate Methodology? Please choose the correct answer.
- A . To enable access to the SAP ecosystem
- B . To accelerate the initial implementation of SAP S/4HANA
- C . To provide end-to-end integrated application lifecycle management
- D . To manage project and solution documentation
Which component of SAP Activate offers customers a reference solution in the cloud for a quick start? Please choose the correct answer.
- A . SAP Implementation Assistant
- B . SAP Activate Methodology
- C . Guided Configuration
- D . SAP Best Practices
In Which phase does the Transition to Operations work stream start? Please choose the correct answer.
- A . Explore
- B . Realize
- C . Deploy
- D . Prepare
What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-premise? Please choose the correct answer.
- A . Key Deliverable
- B . Scenario
- C . Work Stream
- D . Task
Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase? There are 2 correct answers to this question.
- A . Sprint Backlog Template
- B . RICEF Specification Template
- C . Solution Validation Workshop
- D . Quality Gate Checklist
In which tools can the project team across the SAP Activate Methodology content including accelerators? There are 2 correct answers to this question.
- A . SAP Community Network
- B . Roadmap Viewer
- C . SAP Jam
- D . SAP Service Marketplace
Which of the following activities are part of the Deploy Phase of a Landscape Transformation journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question.
- A . Solution Activation
- B . Optimize software Change Control Management
- C . Training delivery
- D . Access organizational and production readiness
What is the best target environment for a System Conversion journey is as described in the SAP Activate methodology? Please choose the correct answer.
- A . SAP Hybris
- B . SAP S/4HANA Cloud Edition
- C . SAP S/4HANA On-Premise Edition
- D . Hybrid of SAP S/4HANA Cloud Edition and SAP S/4HANA On-Premise Edition
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer.
- A . Start with executable content
- B . Limited involvement of business stakeholders
- C . Waterfall approach
- D . Design-based
Which of the following building blocks are part of the SAP S/4HANA platform? There are 2 correct answers to this question.
- A . SAP Fiori UX
- B . SAP HANA in-memory database
- C . SAP Solution Manager
- D . LOB Cloud Solution
What do you do during post cutover? Please choose the correct answer.
- A . Setup Operational Support
- B . Perform the Verification Session of the SAP Going Live Check
- C . Perform Technical System Test
- D . Conduct Organizational Readiness Check
In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the customer? Please choose the correct answer.
- A . Explore
- B . Deploy
- C . Realize
- D . Prepare
What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question.
- A . Premium engagement ready
- B . On-premise only
- C . Fixed scope
- D . Validate solution
- E . Start with SAP Best Practices
According to the Definition of Done, which activity must be completed for each sprint? Please choose the correct answer.
- A . End user training must be delivered
- B . Solution must be built and configured in the development system (DEV)
- C . Functionality must be tested in the Quality system (QAS)
- D . Functionality must be released to the business
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer.
- A . Deploy
- B . Explore
- C . Prepare
- D . Realize
What is the most granular level of the methodology you can view in the Roadmap Viewer? Please choose the correct answer.
- A . Scenario
- B . Task
- C . Deliverables
- D . Phase
What is SAP Activate? Please choose the correct answer.
- A . A step-by-step instruction on how to remove from SAP best practices to your custom solution
- B . A methodology for each of the deployment modes (cloud, on-premise, hybrid)
- C . A bundle of ASAP, SAP Launch, and Rapid Deployment Solutions
- D . A combination of SAP best practices, methodology, and guided configuration
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition? Please choose the correct answer.
- A . SAP Best Practices
- B . Rapid prototyping
- C . Project team training
- D . Full project SCRUM
What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices? Please choose the correct answer.
- A . Activate and apply SAP Best Practices content with the self-service configuration UI
- B . Activate and apply SAP Best Practices with SAP Solution Manager
- C . Apply SAP Best Practices with the Configure your Solution application
- D . Assemble and apply SAP Best Practices to the system
What are the responsibilities of the Product Owner in release and sprint planning? There are 2 correct answers to this question.
- A . Analyze the functional and technical dependencies between the user stories
- B . Define objectives for each release
- C . Prioritize backlog user stories by business priority
- D . Estimate the backlog user stories
Which of the following content best outlines the scope of the Integration Test? Please choose the correct answer.
- A . a. Prototype
- B . Delta/gap solutions
- C . Data flows with non-SAP application
- D . a. Prototype
- E . Delta configuration
- F . Data flows between SAP solutions
- G . a. Solution baseline
- H . Delta/gap solutions
- I . Data flows with non-SAP application
- J . a. Solution baseline
- K . Delta configuration
- L . Data flows between SAP solutions
What are deliverables of the Application: Integration work stream in the prepare phase? There are 3 correct answers to this question.
- A . Fit/Gap Analysis
- B . Data Cleansing
- C . Security Checks
- D . Adaptation Specifications
- E . Network Connectivity Checks
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer.
- A . Navigate by assigned Delivery Mode
- B . Navigate by RACI matrix accountability
- C . Navigate by work stream
- D . Navigate by Project Team Member Role