What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices? Please choose the correct answer.
- A . Activate and apply SAP Best Practices content with the self-service configuration UI
- B . Activate and apply SAP Best Practices with SAP Solution Manager
- C . Apply SAP Best Practices with the Configure your Solution application
- D . Assemble and apply SAP Best Practices to the system
What are the responsibilities of the Product Owner in release and sprint planning? There are 2 correct answers to this question.
- A . Analyze the functional and technical dependencies between the user stories
- B . Define objectives for each release
- C . Prioritize backlog user stories by business priority
- D . Estimate the backlog user stories
Which of the following content best outlines the scope of the Integration Test? Please choose the correct answer.
- A . a. Prototype
- B . Delta/gap solutions
- C . Data flows with non-SAP application
- D . a. Prototype
- E . Delta configuration
- F . Data flows between SAP solutions
- G . a. Solution baseline
- H . Delta/gap solutions
- I . Data flows with non-SAP application
- J . a. Solution baseline
- K . Delta configuration
- L . Data flows between SAP solutions
What are deliverables of the Application: Integration work stream in the prepare phase? There are 3 correct answers to this question.
- A . Fit/Gap Analysis
- B . Data Cleansing
- C . Security Checks
- D . Adaptation Specifications
- E . Network Connectivity Checks
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer.
- A . Navigate by assigned Delivery Mode
- B . Navigate by RACI matrix accountability
- C . Navigate by work stream
- D . Navigate by Project Team Member Role