Referring to the exhibit, which cable will be required to non-disruptively migrate to the new switches?
Click the Exhibit button.
A customer wants to replace their ONTAP cluster CN1610 switches with Cisco Nexus 3132Q-V switches. They want to perform a non-disruptive upgrade.
Referring to the exhibit, which cable will be required to non-disruptively migrate to the new switches?
A . a 10GbE SFP+ to SFP+ cable
B. a 100GbE QSFP28+ to 4x25GbE SFP28+ cable
C. a 40GbE QSFP+ to QSFP+ cable
D. a 40GbE QSFP+ to 4x10GbE SFP+ cable
Answer: D
Explanation:
Reference: https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus9000/sw/7-x/upgrade/guide/b_Cisco_Nexus_9000_Series_NX-OS_Software_Upgrade_and_Downgrade_Guide_Release_7x/b_Cisco_Nexus_9000_Series_NX-OS_Software_Upgrade_and_Downgrade_Guide_Release_7x_chapter_010.html