A company has replicated their critical application VMs to a second data center in another region. Their key application includes two database VMs and three application VMs. For proper operation, the database VMs need to start before the application VMs .
What needs to be configured in Veeam to prepare for a disaster
recovery situation?
A . Use a failover plan
B . Use a planned failover
C . Use Instant VM Recovery
D . Use on-click failover
Answer: A
Explanation:
Reference: https://www.veeam.com/virtual-machine-backup-solution-free.html
the course guide veeam say"a presente scenario for one click failover for a group of independent vms, you can set ORDER for the vm´s in the plan, and the delay intervals to make sure that some vms are already running at the moment to the dependent vms start"