A company has replicated their critical application VMs to a second data center in another region. Their key application includes two database VMs and three application VMs. For proper operation, the database VMs need to start before the application VMs.
What needs to be configured in Veeam to prepare for a disaster
recovery situation?
A . Use a failover plan
B . Use a planned failover
C . Use Instant VM Recovery
D . Use on-click failover
Answer: A
Explanation:
Reference: https://www.veeam.com/virtual-machine-backup-solution-free.html
the course guide veeam say"a presente scenario for one click failover for a group of independent vms, you can set ORDER for the vm´s in the plan, and the delay intervals to make sure that some vms are already running at the moment to the dependent vms start"
Latest VMCE2021 Dumps Valid Version with 100 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund