Prior to installation, what should you consider?

You are installing an HPE Nimble HF20 into a customer’s existing rack.

Prior to installation, what should you consider?
A . An HPE Nimble array has left-to-right airflow
B. HPE recommends installing the HPE Nimble array at the top of the rack
C. The HPE Nimble array will require 3-phase power
D. HPE recommends racks with a depth of 1200 mm

Answer: D

Explanation:

Reference: https://h20195.www2.hpe.com/v2/GetPDF.aspx/a00008274enw.pdf