Which role (A-F) should carry them out?

DRAG DROP Teams have been set up to develop different parts of the ‘classroom-based training materials’. Here are three activities related to managing quality. Which role (A-F) should carry them out? Choose only one for each activity. Each role can be used once, more than once, or not at all....

September 29, 2024 No Comments READ MORE +

During which activity (A-E) should they be carried out?

DRAG DROP DIRECTING A PROJECT Here are three actions that are carried out as part of the ‘directing a project’ process. During which activity (A-E) should they be carried out? Choose only one activity for each action. Each activity can be used once, more than once, or not at all....

September 28, 2024 No Comments READ MORE +

Is this appropriate, and why?

ABC Company has a number of projects in progress. The executive of the Health and Safety Training Project is also a member of the project board for two other projects and is very busy. As a result, during this initiation stage, the executive has appointed another person to carry out...

September 28, 2024 No Comments READ MORE +

Which of the following statements is true of the business interest on the project?

Which of the following statements is true of the business interest on the project?A . Ensures the project provides value for moneyB . Ensures the requirements for the project are definedC . Ensures the products produced meet the desired qualityD . Represents the users of the productView AnswerAnswer: A

September 28, 2024 No Comments READ MORE +

Which risk response type (A-F) are they?

DRAG DROP The project is in stage 2. The project manager has heard that a competitor may launch a similar e-learning course much sooner than ABC Company. There is a threat that the earlier launch of a competitor’s course may reduce the profitability of ABC Company training courses. Here are...

September 28, 2024 No Comments READ MORE +

Which of the following roles cannot be combined?

Which of the following roles cannot be combined?A . Executive and Senior UserB . Project Manager and Project SupportC . Project Assurance and Team ManagerD . Senior Suppler and Supplier AssuranceView AnswerAnswer: C

September 28, 2024 No Comments READ MORE +

Which 2 statements explain why the CEO should be appointed as the Executive for this project?

Which 2 statements explain why the CEO should be appointed as the Executive for this project?A . He started the company 25 years ago.B . He knows his job very well.C . He restricts his visits to the engineering area.D . He has the authority to commit resources as required.E...

September 27, 2024 No Comments READ MORE +

Is the team manager’s response appropriate, and why?

The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the ‘e-learning course’ has agreed to...

September 27, 2024 No Comments READ MORE +

Is this an appropriate application of the ‘tailor to suit the project’ principle, and why?

ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be...

September 26, 2024 No Comments READ MORE +

Is this an appropriate action as part of the ‘controlling a stage’ process, and why?

The project board has asked for highlight reports every six weeks during stage 3. As a result, the project manager has asked each team manager for checkpoint reports every six weeks, in order to collate these into the highlight report. The team manager for the ‘marketed courses’ is new to...

September 25, 2024 No Comments READ MORE +