Which 2 statements should be recorded under the Business options heading?
Which 2 statements should be recorded under the Business options heading?A . The re-engineering of selected business functions would not provide the required outcome.B . The lack of up-to-date technology in MFH means a re-engineering of existing services will not necessarily deliver the performance improvements required.C . Use external consultants...
Which 2 alternative actions apply to the proposed Senior Supplier for this project?
Which 2 alternative actions apply to the proposed Senior Supplier for this project?A . Retain because she is responsible for the design of the future Information Technology organization and working practices.B . Add 'Director of Facilities' because he is responsible for the design of the future organization, processes, systems and...
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about roles on the Outsourcing project
HOTSPOT Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about roles on the Outsourcing project. View AnswerAnswer:
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?
The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will...
How well does this apply the 'manage by stages' principle?
The Health and Safety Training Project has been divided into four stages. The executive considers this project to be a compulsory project and has advised the project manager that it is not necessary to produce the project initiation documentation. This would mean that the project would consist of three delivery...
Which action demonstrates application of the 'manage by exception' principle?
Checkpoint reports are being produced monthly. A week after the last checkpoint report was prepared, the team responsible for developing the 'classroom-based training materials' have realized that they will not be able to deliver the materials to the accreditor by the work package completion deadline. Which action demonstrates application of...
Is this appropriate, and why?
The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must submit all invoices within one week of project closure. The project manager will issue a project closure notification informing all suppliers of this invoicing deadline as part of the ‘recommended project closure’ activity....
Who is responsible for ensuring that the value-for-money solution is constantly reassessed?
Who is responsible for ensuring that the value-for-money solution is constantly reassessed?A . Business AssuranceB . Senior UserC . Corporate or Programme ManagementD . Reject SupportView AnswerAnswer: A
Is this appropriate, and why?
The external team manager for the ‘e-learning course’ has reviewed the quality register to ensure all quality activities have been completed. The ‘e-learning course’ has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is...
Which 2 statements explain why Central Records should be appointed as Project Support for this project?
Which 2 statements explain why Central Records should be appointed as Project Support for this project?A . They control the receipt, identification, versions, storage and issue of all project products within the company's projects.B . They already exist within the organization and have been with the company for many years.C...