PRINCE2 Exam PRINCE2Practitioner PRINCE2 Practitioner Exam Online Training
PRINCE2 Exam PRINCE2Practitioner Online Training
The questions for PRINCE2Practitioner were last updated at Feb 02,2025.
- Exam Code: PRINCE2Practitioner
- Exam Name: PRINCE2 Practitioner Exam
- Certification Provider: PRINCE2 Exam
- Latest update: Feb 02,2025
The Health and Safety Training Project is part of a programme of strategic expansion, which is important for ABC Company’s continued operation. At the end of stage 2, the estimated project costs are greater than the expected benefits in the business case. The project board has reviewed the situation and asked programme management to decide whether the project should be closed prematurely. Is this an appropriate application of the ‘manage by stages’ principle, and why?
- A . Yes, because decisions about closure should be escalated to programme management, unless otherwise instructed.
- B . Yes, because the project board should escalate significant decisions to programme management.
- C . No, because this contradicts the ‘manage by exception’ principle.
- D . No, because the project board should decide whether to continue with the project.
The executive has set the following tolerances for stage 2:
Time (+/- 1 week)
Cost (+/- £20,000)
Scope (using MoSCoW prioritization technique)
Risk (based on the risk appetite defined in the risk management approach)
These tolerances have been recorded in the stage plan. The project manager will report progress regularly via highlight reports to the project board and use exception reports to raise exceptions. In addition, the project assurance role will monitor the stage to provide confidence to the project board that exceptions are being reported.
How well does this apply the ‘manage by exception’ principle, and why?
- A . It applies the principle well, because tolerances should be set for the related aspects of project performance for each stage.
- B . It applies the principle well, because the project manager needs to control the project using discrete management stages.
- C . It applies the principle poorly, because tolerances should be set for each stage against each of the six aspects of project performance.
- D . It applies the principle poorly, because it is the regular reporting of progress that should give the project board the required confidence.
During stage 3, the operational staff that handle course bookings asked for the project scope to be increased for an online booking function. The additional product has been as it will enable them to process bookings more quickly and accurately.
Is this an appropriate application of the ‘focus on products’ principle, and why?
- A . Yes, because the goal is to seek opportunities to implement improvements after the life of the project.
- B . Yes, because the project needs to fulfill stakeholder expectations by delivering the products required.
- C . No, because there needs to be an understanding of the products from the start of the project.
- D . No, because existing product descriptions provide a means to estimate effort to planning.
ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project.
Is this an appropriate application of the ‘tailor to suit the project’ principle, and why?
- A . Yes, because the project manager can adapt or combine PRINCE2 process to suit the project.
- B . Yes, because the standard course development structure should be tailored to suit the project.
- C . No, because a simple project should have no more than two management stages.
- D . No, because the standard course development structure should be applied to the project.
During stage 3, project costs are increasing but there will still be a positive return on investment, as documented in the business case. However, corporate management has recently revised its targets for return on investment and has decided to stop the project as it will not meet the new targets.
Is this an appropriate application of the ‘continued business justification’ principle?
- A . Yes, because changes in corporate strategy may impact a project’s justification.
- B . Yes, because a change in a project’s justification should trigger premature closure.
- C . No, because the project business case still justifies a project.
- D . No, because changes in corporate strategy should not impact a project once authorized.
One of the senior managers of the company that is developing the ‘e-learning course’ has worked with ABC Company before. The team manager for the delivery of the ‘e-learning course’ has looked on ABC Company’s intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to discuss this project.
Is this an appropriate application of the ‘learn from experience’ principle, and why?
- A . Yes, because the project involves more than one organization.
- B . Yes, because the team manager should actively look for useful information.
- C . No, because the senior manager should advise the team manager of any lessons.
- D . No, because every project is unique and should deliver specific business objectives
During stage 3, a work package was assigned to produce the ‘planned pilot courses’. The product’s quality criteria were defined and baselined before the work package was agreed.
Which principle is being applied, and why?
- A . ‘Focus on products’, because delivering a product’s complete set of features is more important than delivering it on time or to cost.
- B . ‘Focus on products’, because a product should be agreed and defined to a reasonable extent before production begins.
- C . ‘Continued business justification’, because the business justification is partly defined in the product description of a specialist product.
- D . ‘Continued business justification’, because both work activities and products contribute to the success of the project.
Checkpoint reports are being produced monthly. A week after the last checkpoint report was prepared, the team responsible for developing the ‘classroom-based training materials’ have realized that they will not be able to deliver the materials to the accreditor by the work package completion deadline.
Which action demonstrates application of the ‘manage by exception’ principle?
- A . The team manager reports the issue in the next checkpoint report.
- B . The team manager immediately produces an exception plan to replace the current plan.
- C . The team manager immediately reports the issue to the project manager.
- D . The team manager raises a risk that the deadline may be missed.
ABC Company produces a corporate business plan which includes the targets for the next 12 months. For the Health and Safety Training Project, a feasibility study was carried out and, as a result, the expected sales were included in this plan. During the ‘starting up a project’ process, the executive advised the project manager that the corporate business plan provides sufficient justification to initiate the project.
Is this a correct application of the ‘continued business justification’ principle, and why?
- A . Yes, because the executive is responsible for the project’s continued business justification.
- B . Yes, because the business justification needs to be recorded and approved in some form.
- C . No, because the feasibility study provides sufficient business justification for the project.
- D . No, because business justification is not required until the ‘initiating a project’ process.
The government agency held a seminar for training organizations to discuss the approach to accreditation for new health and safety courses. The project manager attended on behalf of ABC Company. Other training organizations described delays that had occurred when accrediting course material in the past. As a result, the project manager has produced a report recommending ways to improve the ‘classroom-based training materials’ to avoid such delays.
Is this an appropriate application of the principle ‘learn from experience’, and why?
- A . Yes, because it ensures that risks to accreditation are recorded effectively.
- B . Yes, because opportunities to improve should be recorded and acted upon.
- C . No, because competitors’ experiences are not relevant to ABC projects.
- D . No, because this is an example of improved business justification.