Which 2 alternative actions apply to the proposed supplier assurance for this project?
- A . Retain because he has a professional facilities qualification and so is in a position to specify the needs of his division.
- B . Retain because he will be able to advise on many of the products that will enable outsourcing to happen, such as the 10-year outsourcing service contract.
- C . Retain because he is well-regarded within the Ministry because of the efficiencies, superb service and savings he has achieved in the Facilities Division.
- D . Add ‘Outcome Account Manager’ because he will advise on potential changes and their impact on the integrity of the project’s products.
- E . Remove because he is involved with the project and is therefore NOT independent.
Which 2 alternative actions apply to the proposed user assurance for this project?
- A . Retain because they are both very positive about outsourcing the selected business functions.
- B . Retain because their divisions will be the major users of the outsourced services and they can provide the user perspective on the impact of any proposed changes.
- C . Remove because neither of these individuals are from the business functions to be outsourced.
- D . Retain because selecting only one of them may cause unnecessary conflict.
- E . Retain because they are able to help identify stakeholders and their communication requirements.
HOTSPOT
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about roles on the Outsourcing project.
Question Set 3
Which of the following is False?
A Successful project management team should.
- A . Have business, user and supplier stakeholder representation
- B . Never be reviewed as members should stay with the team for the duration
- C . Ensure appropriate governance by defining responsibilities for directing, managing and delivering the project and clearly defining accountability at all levels
- D . Have an effective strategy to manage communication flows to and from stakeholders
Which of the following statements is true of the business interest on the project?
- A . Ensures the project provides value for money
- B . Ensures the requirements for the project are defined
- C . Ensures the products produced meet the desired quality
- D . Represents the users of the product
Which of the following represents the four key characteristics a good Project board should display?
- A . Authority, Credibility, Commitment, Availability
- B . Authority, Credibility, Delegation, Availability
- C . Authority, Availability, Connections, Delegation
- D . Authority, Credibility, Connections, Delegation
In which Management product would the Project Board specify where the authority for change requests lies?
- A . Risk Management Strategy
- B . Quality Management Strategy
- C . Communication Strategy
- D . Configuration Management Strategy
Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?
- A . Project Assurance
- B . Project Manager
- C . Corporate or Programme Management
- D . Project Support
Which of the following roles cannot be combined?
- A . Executive and Senior User
- B . Project Manager and Project Support
- C . Project Assurance and Team Manager
- D . Senior Suppler and Supplier Assurance
DRAG DROP
ORGANIZATION
Use the ‘Additional Information’ in the Scenario Booklet to answer this question.
Here are three individuals who work for ABC Company.
Which project management team role (A-F) would be the most appropriate for each individual? Choose only one role for each individual. Each role can be used ONCE, or not at all.