Which is a purpose of the quality theme?
- A . To define the specific conditions that enable a product to be usable
- B . To determine how the means of delivering products is communicated
- C . To evaluate whether the project continues to be achievable
- D . To assess any potential improvements to a product
C
Explanation:
Reference: https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_69&showNav =true&expandNav=true
Which is a purpose of the plans theme?
- A . To identify any deviations from the project’s objectives
- B . To control any approved changes to the baseline
- C . To monitor actual achievements against those planned
- D . To communicate the approach for delivering products
Which is a reason for releasing a product into a staging area?
- A . It enables the faster delivery of changes
- B . It supports regulatory compliance checking
- C . It enables a phased Waterfall approach
- D . It supports management by exception
B
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_170&showNav=t rue&expandNav=true#:~:text=Typical%20reasons%20for%20inclusion%20of,of%20validati on%20and%20verification%20process
Which statement describes the Kanban approach?
- A . It is used to make system improvements using visualization and by controlling work in progress
- B . It is an iterative timeboxed approach that helps teams generate value
- C . It was originally focused in creating new companies and is now used to speed up product delivery
- D . It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
A
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_244
What is an epic?
- A . A low-level requirement
- B . A fine-grained user story
- C . A detailed feature
- D . A high-level requirement
D
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_160&showNav=t rue&expandNav=true
Which process can take place during a release review workshop?
- A . Controlling a stage
- B . Managing product delivery
- C . Managing a stage boundary
- D . Directing a project
Which statement about the ‘protect the level of quality’ target is CORRECT?
- A . It is achieved by allowing enough time for testing
- B . It is achieved by using the same team members
- C . It gives confidence on the progress of the project
- D . It delivers the early realization of benefits
D
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41#:~:text=PRINCE2%20Agile%20protects%20the%20level,the%20quality%20level%20is%20met
Which is often used during a retrospective to capture lessons?
- A . A Glad! Sad! Mad! board
- B . A Kanban board
- C . A burn chart
- D . A Gantt chart
A
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_120&showNav=t rue&expandNav=true
Which statement explains how the ‘learn from experience’ principle is applied in an agile context?
- A . It focuses on the prioritization and decomposition of requirements
- B . It integrates releases within management stages
- C . It is supported by the ‘inspect and adapt’ concept
- D . It provides guidance on mapping PRINCE2 roles to an agile environment
C
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_46
How does agile address the risk associated with the project not being fully understood at the beginning?
- A . By allowing a lot of detail at the start
- B . By avoiding too much detail at the start
- C . By requiring details at the start
- D . By preventing the analysis of details at the start