Which role is responsible for creating Checkpoint Reports?
- A . Senior Supplier
- B . Team Manager
- C . Change Authority
- D . Project Support
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
- A . project cost tolerance
- B . stage cost tolerance
- C . Work Package cost tolerance
- D . product cost tolerance
Which is a true statement about time-driven controls?
- A . Time-driven controls are used for monitoring the progress of Work Packages and management stages
- B . Time-driven controls take place when specific events happen
- C . Time-driven controls are produced at the end of a stage
- D . An Exception Report is a time-driven control
Which is a true statement about time-driven controls?
- A . Time-driven controls are used for monitoring the progress of Work Packages and management stages
- B . Time-driven controls take place when specific events happen
- C . Time-driven controls are produced at the end of a stage
- D . An Exception Report is a time-driven control
Which is a true statement about time-driven controls?
- A . Time-driven controls are used for monitoring the progress of Work Packages and management stages
- B . Time-driven controls take place when specific events happen
- C . Time-driven controls are produced at the end of a stage
- D . An Exception Report is a time-driven control
If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
- A . Only 1 is true
- B . Only 2 is true
- C . Both 1 and 2 are true
- D . Neither 1 or 2 are true
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
- A . Progress
- B . Change
- C . Organization
- D . Quality
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
- A . Corporate group
- B . Project Board
- C . Project Assurance
- D . Executive
Which is a FALSE statement about technical stages?
- A . Can overlap with other technical stages
- B . Typified by the use a particular set of specialist skills
- C . Include the Managing a Stage Boundary process activities
- D . Can span more than one management stage
How should the Team Manager report that tolerances are forecast to be exceeded?
- A . Create an Exception Report
- B . Create a Highlight Report
- C . Raise an issue
- D . Grant a concession