PRINCE2 Exam PRINCE2 7 Foundation PRINCE2 7 Foundation written Exam Online Training
PRINCE2 Exam PRINCE2 7 Foundation Online Training
The questions for PRINCE2 7 Foundation were last updated at Nov 22,2024.
- Exam Code: PRINCE2 7 Foundation
- Exam Name: PRINCE2 7 Foundation written Exam
- Certification Provider: PRINCE2 Exam
- Latest update: Nov 22,2024
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
- A . Product Description
- B . Team Plan
- C . Work Package
- D . Stage Plan
Which is a purpose of the Directing a Project process?
- A . Create and authorize the project mandate
- B . Ensure that work on products allocated to the team is authorized and agreed
- C . Control the day-to-day running of the project
- D . Delegate day-to-day management of the project to the Project Manager
Which is a purpose of the Directing a Project process?
- A . Provide the information required to confirm if it is worthwhile to initiate a project
- B . Enable overall control of a project to be exercised by the Project Board
- C . Establish the level of control required by the Project Board after initiation.
- D . Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Which is an objective of the Directing a Project process?
- A . Create and authorize the project mandate
- B . Provide management control and direction
- C . Control the day-to-day running of the project
- D . Provide accurate progress information to the Project Manager
In what process is the authorization to deliver the project’s products given?
- A . Starting up a Project
- B . Initiating a Project
- C . Managing a Stage Boundary
- D . Directing a Project
Who should act as the communication channel between a project and corporate or programme management?
- A . Project Board
- B . Project Assurance
- C . Project Manager
- D . Project Support
Which statement about the Directing a Project process is true?
- A . Provides a mechanism for the Project Board to assure that there is continued business justification
- B . Covers the day-to-day activities of the Project Manager
- C . Ensures there are regular progress meetings
- D . Begins on completion of the Initiating a Project process
Which statement about the Directing a Project process is true?
- A . Provides a mechanism for the Project Board to assure that there is continued business justification
- B . Covers the day-to-day activities of the Project Manager
- C . Ensures there are regular progress meetings
- D . Begins on completion of the Initiating a Project process
Which statement about the Directing a Project process is true?
- A . Provides a mechanism for the Project Board to assure that there is continued business justification
- B . Covers the day-to-day activities of the Project Manager
- C . Ensures there are regular progress meetings
- D . Begins on completion of the Initiating a Project process
The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
- A . Only 1 is true
- B . Only 2 is true
- C . Both 1 and 2 are true
- D . Neither 1 or 2 are true