Which should be funded by a change budget?
- A . Increase in agreed scope
- B . Initiation stage
- C . Change Authority
- D . Handover activities
Which should be funded from a change budget?
- A . The Starting up a Project process
- B . A fallback plan
- C . An agreed change to the scope of a project
- D . A change to a plan, within allocated tolerances, due to poor estimating
Which is the Issue Register NOT used for?
- A . Capture external events that are impacting a stage
- B . Record information about a deviation in stage tolerance
- C . Capture any threats or opportunities that might have an impact on a stage
- D . Record any problems identified when authorizing a Work Package
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
- A . Checkpoint Report
- B . Highlight Report
- C . Issue Report
- D . Product Status Account
Which is the purpose of the Change theme?
- A . Prevent change to baselined products
- B . Identify, assess and control any potential and approved changes to baselined products
- C . Establish mechanisms to monitor and compare actual achievements against those planned
- D . Assess and control uncertainty
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
- A . Capture
- B . Examine
- C . Propose
- D . Decide
A product can NOT be supplied to meet all of the requirements in its baselined Product Description.
What first action should be taken?
- A . Raise a request for change
- B . Raise an off-specification
- C . Write an Exception Report
- D . Amend the Work Package
A product can NOT be supplied to meet all of the requirements in its baselined Product Description.
What first action should be taken?
- A . Raise a request for change
- B . Raise an off-specification
- C . Write an Exception Report
- D . Amend the Work Package
A product can NOT be supplied to meet all of the requirements in its baselined Product Description.
What first action should be taken?
- A . Raise a request for change
- B . Raise an off-specification
- C . Write an Exception Report
- D . Amend the Work Package
The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
- A . Only 1 is true
- B . Only 2 is true
- C . Both 1 and 2 are true
- D . Neither 1 or 2 are true