Which statement about stages is true?
- A . Management stages should be of the same duration
- B . The use of technical stages is mandatory
- C . The use of management stages is mandatory
- D . Management stages are driven by specialist teams
What product defines the reporting requirements between the Project Manager and Team Manager?
- A . Project Brief
- B . Product Description
- C . Team Plan
- D . Work Package
Whose approval is needed to replace a Stage Plan with an Exception Plan?
- A . Corporate or programme management
- B . Project Board
- C . Project Manager
- D . Team Manager
Which is a difference between management and technical stages?
- A . Management stages require planning and technical stages do not
- B . Technical stages can overlap and management stages cannot
- C . Management stages deliver products and technical stages do not
- D . Technical stages require resources and management stages do not
Which is a purpose of a Lessons Log?
- A . Note any lessons that are raised in Checkpoint Reports
- B . Record that corrective action is being taken
- C . Escalate lessons to the Project Board
- D . Raise improvements with Project Assurance
Which is a true statement about PRINCE2 event-driven controls?
- A . Event-driven controls take place at predefined periodic intervals
- B . Event-driven controls are produced at the frequency defined in a Work Package
- C . Event-driven controls are used for decision making
- D . Checkpoint Reports are event-driven controls
Which is a purpose of an End Project Report?
- A . Identify individuals or groups that need to be told that the project is coming to an end
- B . Review how well the project performed against the Project Initiation Documentation used to authorize it
- C . Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- D . Ensure that key project information is archived and made secure
How many management stages should a PRINCE2 project consist of?
- A . Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
- B . Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
- C . Initiation stage and at least one other management stage to cover the remainder of the project
- D . Start up stage, initiation stage and a closing stage
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
- A . Configuration Item Record
- B . Quality Register
- C . Highlight Report
- D . Checkpoint Report
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
- A . Only corporate or programme management
- B . Only the Project Board
- C . Only the Project Manager
- D . All levels of management