Which product records any project outcomes perceived as negative by stakeholders?
- A . Business Case
- B . Project Plan
- C . Communication Management Strategy
- D . Project Product Description
What is the definition of a project outcome?
- A . A measurable improvement that is perceived as an advantage by one or more stakeholders
- B . The reason for the project
- C . The result of the change derived from using the project’s outputs
- D . The project’s specialist products.
Which is NOT a purpose of a Benefits Review Plan?
- A . Define the period over which the cost-benefit analysis will be based
- B . Describe how to measure the performance of the project’s products in operational use
- C . Define the scope, timing and ownership of the benefit reviews required
- D . Describe how to measure and confirm any benefits that are to be realised after the project is closed
Which product documents the information needed to demonstrate continued business justification?
- A . Business Case
- B . Communication Management Strategy
- C . Project Product Description
- D . Quality Management Strategy
Which is NOT a purpose of a Benefits Review Plan?
- A . Define the period over which the cost-benefit analysis will be based
- B . Describe how to measure the performance of the project’s products in operational use
- C . Define the scope, timing and ownership of the benefit reviews required
- D . Describe how to measure and confirm any benefits that are to be realised after the project is closed
What is an off-specification?
- A . A new requirement
- B . A quality tolerance
- C . A type of issue
- D . A major risk
Which is a type of issue?
- A . A lesson
- B . A request for change
- C . An Exception Report
- D . A risk with an estimated high impact
Which is a typical core activity within configuration management?
- A . Quality assurance
- B . Risk management
- C . Verification and audit
- D . Progress reporting
Which is a typical core activity within configuration management?
- A . Issue management
- B . Quality inspection
- C . Identification
- D . Preparation
What needs to be in place to ensure effective issue and change control?
- A . Configuration management system
- B . Manage by exception
- C . Quality planning
- D . Information needs for stakeholders