Exam4Training

Portfolio management includes prioritising:

Portfolio management includes prioritising:
A . projects and/or programmes that contribute directly to the organisation’s strategic objectives.
B . projects with exceptionally high returns on investment.
C . projects and programmes over business as usual.
D . projects which maximise change over those which maximise investment

Answer: A

Latest APM-PFQ Dumps Valid Version with 354 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version