Which estimation technique should the project manager implement in this context?
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget. Which estimation technique...
What should the project manager do next?
A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project. What should the project manager do...
What should the project manager do first?
A project manager is leading a hybrid project and is collaborating with the client to develop the project contract. Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked...
What should the project manager do next?
A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle. What should the project manager do next?A . Guide the team to determine...
What should the project manager do to engage the team?
A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually. What should the project manager do to engage the team?A . Have one-on-one meetings with team members to improve communication. B. Ask human resources...
What should the team do about the identified risks?
An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?A . Mitigate the risks that are applicable to the current and following iterations. B. Focus on the project deliverables rather than the documented risks. C. Agree that...
How should the project manager help the team resolve the issue?
A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint. How should the project manager help the team resolve the issue?A . Direct the senior-most member to...
What should the project manager do to improve the situation?
A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager....
How should the project manager reply?
At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties. How should the project manager reply?A . Recurrent team meetings are planned to control...
What should the project manager do first?
A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product. What should the project manager do first?A . Set up a meeting with the product owner to discuss the stakeholder's concern. B. Discuss...