What should the project lead recommend?
An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed. What should...
How should the project manager ensure that these changes are managed effectively?
During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives. How should the project manager ensure that these changes are managed effectively?A . Include the changes in the backlog and review priorities with...
What should the project manager do?
A company is going through structural changes. A couple of people will leave the company as their positions were made redundant. The team members are unhappy as they do not understand why the changes are being made when the project is on track. What should the project manager do?A ....
What should the project manager mainly make reference to?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?A . Feedback from the project sponsor B. Agreed-upon key performance indicators (KPIs) C. Input from project stakeholders D. Competencies of...
What should the project manager have done to prevent this?
A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need...
How should the project manager recognize high performance?
A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project. How should the project manager recognize high performance?A . Thank the team member privately to avoid conflict...
What should the project manager verify first?
A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team. What...
What should the project manager do?
A project team is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned. What should the project manager do?A...
How should the project manager deal with this request?
A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity. How should the project manager...
What should the project manager do first?
A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?A . Ask the project team to review and modify all of these reports. B. Ask the sponsor to meet with the stakeholder...