Why is an attendance list important?
For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available Why is an attendance list important?A ....
A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians
DRAG DROP A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians. The project manager now needs to categorize the identified risks Drag each risk type on the left to its...
What does the project manager need to do first in order to have good project performance?
A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches. What does the project manager need to do first in order to have good project performance?A . Coach those team members lacking hybrid knowledge to learn on the...
What should the project manager do?
An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed. What should the project manager do?A ....
What should the project manager do to help in this situation?
A new team member has joined an agile project, replacing a team member who recently left. The project team needs the new team member to speed up their ability to contribute effectively to the project What should the project manager do to help in this situation?A . Assign the new...
What should the project manager do?
An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project What should the project manager do?A...
What should the project manager do?
The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision. What should the project manager do?A ....
What should the project manager have done to prevent this from happening?
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval. What should the project manager have done to...
How should the project manager handle this situation?
A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors. The project is ongoing and uses a hybrid approach. The project will be conducted in multiple sites, with several development...
Which team is performing better?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points Which team is performing better?A . Team A as they have...