What should the project manager do?
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days. What should the project manager do?A . Ask the team to work overtime to complete the deliverable on time B. Evaluate the situation and identify...
What should the project manager do first?
A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization. What should the project manager do first?A . Start developing a business case. B. Start a strengths, weaknesses, opportunities and threats...
What is one of the key activities that the project manager should undertake to ensure company success?
A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings What is one of the key activities that the project manager should undertake to ensure company success?A . Review the project...
What should the project manager do in this situation?
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts. What should the project manager do in this situation?A . Work to understand the key stakeholder's concerns and provide feedback in regular project status reports B. Arrange an...
What should the project manager do to increase the project's chances of success?
A research and development department is planning to develop a product that will introduce a new line of business for the organization. What should the project manager do to increase the project's chances of success?A . Plan a working session focusing on the scope, vision, and mission of the initiative...
What should the project manager do to address this issue?
A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease . What should the project manager do to address this issue?A . Force the team members to work from one location. B. Develop protocols for resolving conflicts between team members C. Obtain...
What key activity is needed to ensure the project's success?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the...
What should the project manager do to realize benefits?
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch What should the project manager do to realize benefits?A ....
What should the project manager do?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team . What should the project manager do?A . Ask the team member to enter this potential schedule delay in the risk register. B. Explain...
What is the first step the project manager should take to gather customer requirements?
A new project manager is planning an information security project for a company that resides in different countries . What is the first step the project manager should take to gather customer requirements?A . Conduct a stakeholder analysis to identify how regional policies may influence needs B. Request relevant stakeholders...