What should the project manager do?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project. What should the project...
An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams
DRAG DROP An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right View AnswerAnswer:
What two actions should the project manager take'?
A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline What two actions should the project manager take'? (Choose two)A . Send letters to the neighbors and ask them...
Which two stakeholders can help the project manager determine and address compliance requirements?
A project manager is working on the implementation of new phases in the production process of a regulated industry . Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)A . Risk steering committee B. Functional managers C. Board of directors D. Advisory team panel...
Based on the new timeline, what should the project manager do?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?A . Plan for overtime apply crashing and fast tracking and...
How should the project manager proceed?
During the closing process, the project manager learns that one deliverable is not meeting customer expectations. How should the project manager proceed?A . Ask the customer to issue a change request with the information to analyze and provide a solution. B. Review the deliverable requirements, check the customer approval criteria,...
What should the project manager do next?
During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request. What should the project manager do next?A . Discuss approval of the change request in the next project meeting B. Perform a...
A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.
A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool....
What should the project manager do?
A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change. What should the project manager do?A . Make the decision on behalf of the organization B. Review the...
What is the cause for this communication gap?
A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members What is the cause for this communication gap?A . The project sprint board has not been updated B. Daily standup meetings were not held...