Organizations perceive risks as:

Organizations perceive risks as:A . events that will inevitably impact project and organizational objectives.B . the effect of uncertainty on their project and organizational objectives.C . events which could have a negative impact on project and organizational objectives.D . the negative impact of undesired events on their project and organizational...

March 5, 2020 No Comments READ MORE +

Project management processes ensure the:

Project management processes ensure the:A . alignment with organizational strategyB . efficient means to achieve the project objectivesC . performance of the project teamD . effective flow of the project throughout its life cycleView AnswerAnswer: D

March 5, 2020 No Comments READ MORE +

A tool and technique used in the Develop Project Charter process is:

A tool and technique used in the Develop Project Charter process is:A . change control toolsB . expert judgmentC . meetingsD . analytical techniquesView AnswerAnswer: B

March 5, 2020 No Comments READ MORE +

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:A . ResponsesB . AppetiteC . ToleranceD . AttitudeView AnswerAnswer: A

March 4, 2020 No Comments READ MORE +

Which input to the Plan Risk Management process provides information on high-level risks?

Which input to the Plan Risk Management process provides information on high-level risks?A . Project charterB . Enterprise environmental factorsC . Stakeholder registerD . Organizational process assetsView AnswerAnswer: A

March 4, 2020 No Comments READ MORE +

Project Stakeholder Management focuses on:

Project Stakeholder Management focuses on:A . project staff assignmentsB . project tea m acquisitionC . managing conflicting interestsD . communication methodsView AnswerAnswer: C

March 3, 2020 No Comments READ MORE +

Projects are undertaken by an organization to support the:

Projects are undertaken by an organization to support the:A . Product performance.B . Budget process.C . Collective capabilities.D . Organizational strategy.View AnswerAnswer: D

March 3, 2020 No Comments READ MORE +

Which process is included in the Project Integration Management Knowledge Area?

Which process is included in the Project Integration Management Knowledge Area?A . Manage Project TeamB . Collect RequirementsC . Sequence ActivitiesD . Direct and Manage Project WorkView AnswerAnswer: D

March 3, 2020 No Comments READ MORE +

The formal and informal interaction with others in an organization industry, or professional environment is known as:

The formal and informal interaction with others in an organization industry, or professional environment is known as:A . negotiationB . organizational theoryC . meetingD . networkingView AnswerAnswer: D

March 3, 2020 No Comments READ MORE +

Which type of managers do composite organizations involve?

Which type of managers do composite organizations involve?A . Functional managers and manager of project managersB . Functional managers onlyC . Project managers onlyD . Technical managers and project managersView AnswerAnswer: C

March 3, 2020 No Comments READ MORE +