Which of the following investigates the likelihood that each specific risk will occur?
Which of the following investigates the likelihood that each specific risk will occur?A . Risk registerB . Risk auditsC . Risk urgency assessmentD . Risk probability and impact assessmentView AnswerAnswer: D
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:A . influencingB . leadershipC . motivationD . coachingView AnswerAnswer: A
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
What is a hierarchically organized depiction of the identified project risks arranged by risk category?A . Risk registerB . Risk breakdown structure (RBS)C . Risk management planD . Risk categoryView AnswerAnswer: B
Assigned risk ratings are based upon:
Assigned risk ratings are based upon:A . Root cause analysis.B . Risk probability and impact assessment.C . Expert judgment.D . Revised stakeholders' tolerances.View AnswerAnswer: B
The scope management plan is a subsidiary of which project document?
The scope management plan is a subsidiary of which project document?A . Schedule management planB . Project management planC . Quality management planD . Resource management planView AnswerAnswer: B
Which stakeholder approves a project's result?
Which stakeholder approves a project's result?A . CustomerB . SponsorC . SellerD . Functional managerView AnswerAnswer: A
An output of the Develop Project Team process is:
An output of the Develop Project Team process is:A . change requestsB . team performance assessmentsC . project staff assignmentsD . project documents updatesView AnswerAnswer: B
The stakeholder register is an output of:
The stakeholder register is an output of:A . Identify Stakeholders.B . Plan Stakeholder Management.C . Control Stakeholder Engagement.D . Manage Stakeholder Engagement.View AnswerAnswer: A
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?A . Procurement documentsB . Communications planC . Project charterD . Stakeholder registerView AnswerAnswer: C
The component of the risk management plan that documents how risk activities will be recorded is called:
The component of the risk management plan that documents how risk activities will be recorded is called:A . trackingB . scopingC . timingD . definingView AnswerAnswer: A