Stakeholder satisfaction should be managed as a key project:

Stakeholder satisfaction should be managed as a key project:A . BenefitB . InitiativeC . ObjectiveD . ProcessView AnswerAnswer: C

March 14, 2020 No Comments READ MORE +

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?A . Requirements documentationB . Requirements traceability matrixC . Project management plan updatesD . Project documents updatesView AnswerAnswer: B

March 14, 2020 No Comments READ MORE +

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?A . Organizational standard processesB . Marketplace conditionsC . Historical informationD . TemplatesView AnswerAnswer: B

March 14, 2020 No Comments READ MORE +

In which Knowledge Area is the project charter developed?

In which Knowledge Area is the project charter developed?A . Project Cost ManagementB . Project Scope ManagementC . Project Time ManagementD . Project Integration ManagementView AnswerAnswer: D

March 14, 2020 No Comments READ MORE +

Which element does a project charter contain?

Which element does a project charter contain?A . Management reservesB . Work breakdown structureC . Stakeholder listD . Stakeholder registerView AnswerAnswer: C

March 13, 2020 No Comments READ MORE +

Through whom do project managers accomplish work?

Through whom do project managers accomplish work?A . Consultants and stakeholdersB . Stakeholders and functional managersC . Project team members and consultantsD . Project team members and stakeholdersView AnswerAnswer: D

March 13, 2020 No Comments READ MORE +

Which cost is associated with nonconformance?

Which cost is associated with nonconformance?A . LiabilitiesB . InspectionsC . TrainingD . EquipmentView AnswerAnswer: A

March 13, 2020 No Comments READ MORE +

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?A . Feedback analysisB . Stakeholder analysisC . Communication management planD . Stakeholder management planView AnswerAnswer: D

March 13, 2020 No Comments READ MORE +

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?A . PushB . PullC . InteractiveD . IterativeView AnswerAnswer: B

March 13, 2020 No Comments READ MORE +

In project management, a temporary project can be:

In project management, a temporary project can be:A . Completed without planningB . A routine business processC . Long in durationD . Ongoing to produce goodsView AnswerAnswer: C

March 12, 2020 No Comments READ MORE +