What is one of the objectives of Project Risk Management?
What is one of the objectives of Project Risk Management?A . Decrease the probability and impact of an event on project objectives.B . Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.C . Increase the probability and impact of...
High-level project risks are included in which document?
High-level project risks are included in which document?A . Business caseB . Risk breakdown structureC . Project charterD . Risk registerView AnswerAnswer: C
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?A . Cause-and-effect diagramB . HistogramC . Control chartD . Scatter diagramView AnswerAnswer: D
An input required in Define Scope is an organizational:
An input required in Define Scope is an organizational:A . structure.B . process asset.C . matrix.D . breakdown structure.View AnswerAnswer: B
The Verify Scope process is primarily concerned with:
The Verify Scope process is primarily concerned with:A . formalizing acceptance of the completed project deliverables.B . accuracy of the work deliverables.C . formalizing approval of the scope statement.D . accuracy of the work breakdown structure (WBS).View AnswerAnswer: A
Which of the following is TRUE about most project life cycles?
Which of the following is TRUE about most project life cycles?A . Staffing level is highest at the start.B . The stakeholders' influence is highest at the start.C . The level of uncertainty is lowest at the start.D . The cost of changes is highest at the start.View AnswerAnswer: B
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?A . Stakeholder registerB . Scope management planC . Stakeholder management planD . Project charterView AnswerAnswer: A
The purpose of developing a project scope management plan is to:
The purpose of developing a project scope management plan is to:A . Manage the timely completion of the project.B . Ensure that the project includes all of the work required.C . Make sure the project will satisfy the needs for which it was begun.D . Reduce the risk of negative...
The process of defining how the project scope will be validated and controlled is known as:
The process of defining how the project scope will be validated and controlled is known as:A . Define Scope.B . Develop Project Management Plan.C . Plan Scope Management.D . Plan Quality Management.View AnswerAnswer: C
Identify Risks is part of which Process Group?
Identify Risks is part of which Process Group?A . PlanningB . ExecutingC . ClosingD . InitiatingView AnswerAnswer: A