What should the project manager do?
An organization is completing a critical milestone during the construction of residential properties. The project is fully sponsored by the government. Ten days prior to completion of this key project phase: affected community members begin a four-day protest causing the project to be put on hold. What should the project...
What part of the project will this complete?
After preparation of the project management plan, the project manager schedules a meeting with Key stakeholders. What part of the project will this complete?A . PlanningB . EvaluationC . ExecutionD . InitiationView AnswerAnswer: A
A recently promoted project manager must facilitate the weekly status update meeting, what should the project manager do to ensure a productive meeting?
A recently promoted project manager must facilitate the weekly status update meeting, what should the project manager do to ensure a productive meeting?A . Avoid or smooth over any disagreements.B . Carefully read the latest meeting minutes.C . Limit attendance to the project team and stakeholders.D . Circulate a defined...
What should the project manager do?
A vendor communicates that the delivery of a project item will be delayed by two weeks. What should the project manager do?A . Conduct a variance analysis.B . Implement the Perform Integrated Change Control processC . Review the contract clause for liquidated damagesD . Identify a way to conduct schedule...
A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?
A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?A . Equal to 1.2B . Less than 1C . Equal to 1D . Greater...
What should the project manager do?
A project manager discovers an enhancement that will improve the design being developed by a subject matter expert (EME). What should the project manager do?A . Disregard the enhancement, as no changes are allowed.B . Ask the expert to implement the enhancement.C . Ask the change control board (CCB) to...
What should the project manager do?
Prior to the implementation of a system upgrade, a team member discovers a critical detect in the current system mat must be fixed. What should the project manager do?A . Take no further actions since the project scope has been finalized.B . Implement the fix and install it with the...
What should the project manager recommend to the project sponsor?
A project to replace a core business system is required by a company's CEO. The CEO appoints a project sponsor, and urges an immediate start to the project. The project sponsor asks the project manager―who has no previous experience with such a complex project―to write the project charter. What should...
What should the project manager have done to avoid this?
A design team discovers that the work breakdown structure (WBS) created by the project manager is missing key tasks. What should the project manager have done to avoid this?A . Reviewed historical information from previous projectsB . Developed an Ishikawa diagramC . Created a requirements traceability matrixD . Sought expert...
What should the project manager do to close the project?
Work on a project passes the customer acceptance test and the customer expresses appreciation. What should the project manager do to close the project?A . Notify the steering committee.B . Obtain a letter of recommendation from the customerC . Obtain formal acceptance from the customerD . Notify the project sponsor...