What should the project manager do?

An organization is completing a critical milestone during the construction of residential properties. The project is fully sponsored by the government. Ten days prior to completion of this key project phase: affected community members begin a four-day protest causing the project to be put on hold. What should the project...

January 2, 2021 No Comments READ MORE +

What part of the project will this complete?

After preparation of the project management plan, the project manager schedules a meeting with Key stakeholders. What part of the project will this complete?A . PlanningB . EvaluationC . ExecutionD . InitiationView AnswerAnswer: A

January 2, 2021 No Comments READ MORE +

A recently promoted project manager must facilitate the weekly status update meeting, what should the project manager do to ensure a productive meeting?

A recently promoted project manager must facilitate the weekly status update meeting, what should the project manager do to ensure a productive meeting?A . Avoid or smooth over any disagreements.B . Carefully read the latest meeting minutes.C . Limit attendance to the project team and stakeholders.D . Circulate a defined...

January 2, 2021 No Comments READ MORE +

What should the project manager do?

A vendor communicates that the delivery of a project item will be delayed by two weeks. What should the project manager do?A . Conduct a variance analysis.B . Implement the Perform Integrated Change Control processC . Review the contract clause for liquidated damagesD . Identify a way to conduct schedule...

January 2, 2021 No Comments READ MORE +

A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?

A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?A . Equal to 1.2B . Less than 1C . Equal to 1D . Greater...

January 2, 2021 No Comments READ MORE +

What should the project manager do?

A project manager discovers an enhancement that will improve the design being developed by a subject matter expert (EME). What should the project manager do?A . Disregard the enhancement, as no changes are allowed.B . Ask the expert to implement the enhancement.C . Ask the change control board (CCB) to...

January 2, 2021 No Comments READ MORE +

What should the project manager do?

Prior to the implementation of a system upgrade, a team member discovers a critical detect in the current system mat must be fixed. What should the project manager do?A . Take no further actions since the project scope has been finalized.B . Implement the fix and install it with the...

January 1, 2021 No Comments READ MORE +

What should the project manager recommend to the project sponsor?

A project to replace a core business system is required by a company's CEO. The CEO appoints a project sponsor, and urges an immediate start to the project. The project sponsor asks the project manager―who has no previous experience with such a complex project―to write the project charter. What should...

January 1, 2021 No Comments READ MORE +

What should the project manager have done to avoid this?

A design team discovers that the work breakdown structure (WBS) created by the project manager is missing key tasks. What should the project manager have done to avoid this?A . Reviewed historical information from previous projectsB . Developed an Ishikawa diagramC . Created a requirements traceability matrixD . Sought expert...

January 1, 2021 No Comments READ MORE +

What should the project manager do to close the project?

Work on a project passes the customer acceptance test and the customer expresses appreciation. What should the project manager do to close the project?A . Notify the steering committee.B . Obtain a letter of recommendation from the customerC . Obtain formal acceptance from the customerD . Notify the project sponsor...

January 1, 2021 No Comments READ MORE +