What tool or technique is the team using?
A performance report indicates a variation in a product's specifications. The project manager calls an emergency meeting during which all team members offer suggestions for the possible cause of the variance. What tool or technique is the team using?A . Cause-and-effect diagramB . Scatter diagramC . Matrix diagramD . Root...
A project is nearing completion when the project manager learns that a change in market regulations may impact the project, what sn6uld the project manager do?
A project is nearing completion when the project manager learns that a change in market regulations may impact the project, what sn6uld the project manager do?A . Review the risk management plan.B . Perform a cost-benefit analysis.C . Check the stakeholder register.D . Update the cost baseline.View AnswerAnswer: A
As part of the initiation process, what should the project manager do prior to the planning stage?
A project manager assumes a new project. As part of the initiation process, what should the project manager do prior to the planning stage?A . Define the project sign-off criteria and create a risk registerB . Start gathering requirements and plan the kick-off meeting.C . Develop the project charter and...
What should the project manager do to address this?
As part of a project, a new plant is being constructed in a typhoon-prone area. This may impact the project s schedule and quality. What should the project manager do to address this?A . Conduct the Perform Quantitative Risk Analysis process, and plan a risk response.B . Establish a contingency...
Of what type of risk acceptance is this an example?
A project manager planning various modules for a large-scale software development project has completed a trend analysis of previous projects. The project manager discovers that every project for the last two years has underestimated work and costs by at least 32 percent. The project manager decides to add a 35...
What project scenario does this describe?
A project's budgeted value of work completed is less than the authorized budget for planned work. What project scenario does this describe?A . Project activity is behind schedule.B . The project is on schedule.C . The project is ahead of scheduleD . The earned value (EV) of the project is...
What should the project manager use to determine this?
During a project, several risks are identified. The project manager wants to determine what risks will have the most potential impact. What should the project manager use to determine this?A . Sensitivity analysisB . Expert judgmentC . Probability distributionsD . InterviewingView AnswerAnswer: A
What strategy is the project manager using?
During the execution of an IT project, a project manager warns of the possibility that the main server may fail due to constant, local-area electrical outages. The project manager signs a contract to rent an additional server from a local company. What strategy is the project manager using?A . MitigateB...
What should the project manager do?
A project manager joins an ongoing project. During a weekly status meeting, the team informs the project manager that the project plan indicates that quality assurance will be performed during the closing phase. What should the project manager do?A . Use quality assurance to measure project team performanceB . Continue...
What should company B's project manager consider as an input when developing the project charter?
Company A wants to subcontract the installation of a factory's building management system to company B. After some adjustments and a review of key stakeholder feedback, company B's project manager needs to develop the project charter for approval. What should company B's project manager consider as an input when developing...