What amount should the contractor be paid?

The project manager of a pipeline project hires a construction contractor using a cost plus fixed fee (CPFF) contract, the contractor provides the project manager with an estimate of US$50,000, and a fixed-fee amount of US$5,000. When the pipeline is completed, the construction cost is US$60,000. What amount should the...

January 9, 2021 No Comments READ MORE +

To support the work, what should the project manager do next?

An IT department's deliverable is two weeks late If the deliverable is not completed by the end of the week the project will be placed on hold Within the last two weeks the project manager communicated the issue to the IT department, spoke with the IT project manager and elevated...

January 9, 2021 No Comments READ MORE +

What document is produced from this activity?

A matrixed organization has a history of project schedule and cost overruns. A new project manager learns of this history and wants to avoid the trend. The project manager works with the project team to define, validate, and control all required work to complete the project successfully What document is...

January 9, 2021 No Comments READ MORE +

What would be the critical path(s)?

A project has live finish-to-start (FS) activities - Activity A takes one day. - Activity B follows A and takes five days - Activity C follows B and takes two days. - Activity D follows B and A and takes two days. - Activity E is preceded by C and...

January 9, 2021 No Comments READ MORE +

Which document confirms whether the vendor should do this testing?

The project manager discovers that the vendor did not perform software technical testing. Which document confirms whether the vendor should do this testing?A . Procurement management planB . Statement of work (SOW)C . Scope management plan D Product scope descriptionView AnswerAnswer: B

January 8, 2021 No Comments READ MORE +

What should the project team do to benefit from this phase?

Phase two of a complex, multi-phase project is completed, and the customer accepts the deliverables. What should the project team do to benefit from this phase?A . Measure customer satisfaction.B . Document and share lessons learnedC . Obtain additional resourcesD . Perform a risk analysis.View AnswerAnswer: B

January 8, 2021 No Comments READ MORE +

What should the project manager do first?

All quality controls have passed, and a project deliverable is ready to be released to the customer However, a change request to add new quality criteria has been approved. What should the project manager do first?A . Update the project management planB . Stop the release of the deliverable to...

January 8, 2021 No Comments READ MORE +

What should the project manager do?

A company has a history of implementing system integration projects using their-in-house software with a vendor infrastructure A project manager, new to the company, has no prior experience with vendor integration projects What should the project manager do?A . Refer to the project statement of work (SOW)B . Review the...

January 8, 2021 No Comments READ MORE +

What document should the project manager use to ensure that payment delay information is documented for this project?

A company has a longstanding client who is often late with payment. The company now has a new project with this client. What document should the project manager use to ensure that payment delay information is documented for this project?A . Risk management planB . Historical information and lessons learned...

January 8, 2021 No Comments READ MORE +

What final action should the project manager take before moving to the new project?

A project manager delivered the final project report and is ready to close the project. The company is anxious to start an important project and asks the project manager to start the new assignment immediately What final action should the project manager take before moving to the new project?A ....

January 8, 2021 No Comments READ MORE +