What should the project manager do next in this situation?
During the execution of a maintenance project the contractor submits an offer for additional work. The project manager realizes that the activities billed are included in the initial scope of work. What should the project manager do next in this situation?A . Review the project scope and negotiate with the...
What are two issues that these actions by the project manager could cause?
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion What are two issues that these actions by the project manager could cause? (Choose two)A...
What should the project manager do next with this opportunity?
During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level What should the...
What has happened in this situation?
A project manager for a maintenance project has a contract that is renewed annually. The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year What has happened in this situation?A ....
What should the project manager do to help ensure more collaboration between the teams?
A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution. The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately What should the...
What should the project manager have done to avoid this situation?
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting What should the project manager have done to avoid...
What should the project manager do?
A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks. What should the project manager do?A . Wait for the team to identify and solve the problem independently.B . Move the team member to another task that...
What is the first step the project manager should take to gather customer requirements?
A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?A . Conduct a stakeholder analysis to identify how regional policies may influence needsB . Request relevant stakeholders to...
What should the project manager do first?
A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization. What should the project manager do first?A . Start developing a business case.B . Start a strengths, weaknesses, opportunities and threats...
What should the project manager do first?
A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project. What should the project manager do first?A . Develop the resource management plan and ensure adequate trainingB...