What should the project manager have done to avoid this?

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project...

February 4, 2025 No Comments READ MORE +

How should project X's project manager avoid this situation in the future?

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities...

February 4, 2025 No Comments READ MORE +

What is critical for the risk manager to consider when describing the causes?

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described . What is critical for the risk manager to consider when describing the causes?A . Each cause has a degree of uncertaintyB . Each cause has well defined ownerC . The...

February 2, 2025 No Comments READ MORE +

What should the project manager do next?

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk...

February 1, 2025 No Comments READ MORE +

What should the project manager do?

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others . What should the project manager do?A . Reduce the probabilities of those risks on the risk registerB . Transfer ownership of those risks to the customerC . Implement the risk handling...

January 27, 2025 No Comments READ MORE +

What is the project manager performing in this situation?

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work . What is the project manager performing in this situation?A . Risk mitigationB . Risk transferC . Risk acceptanceD . Risk avoidanceView AnswerAnswer: B Explanation: By...

January 26, 2025 No Comments READ MORE +

How should the risk manager proceed?

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established . How should the risk manager...

January 25, 2025 No Comments READ MORE +

What is the first thing the risk manager should do?

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations . What is the first thing the risk manager should do?A . Highlight this situation to the project managerB . Conduct a cost-benefit analysisC . Change the risk...

January 23, 2025 No Comments READ MORE +

Which document will need to be updated?

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated. Which document will need to be updated?A . Lessons learnedB . Contingency registerC ....

January 23, 2025 No Comments READ MORE +