A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?
A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?A . Review potential next steps with the project team.B . Review the scope of work to determine the prescribed project methodology.C . Review the policies and practices...
Which risk identification technique should the risk manager use?
A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created . Which risk identification technique should the risk manager use?A...
How should the project manager address this concern?
Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company. How should the...
What should the risk manager do with this risk?
A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low. What should the risk manager do with this...
What should the risk management professional do next?
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks. What should the risk management professional do next?A . Perform a sensitivity analysis to the higher-level aggregate activitiesB...
What should the project manager do first?
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG...
What should the risk manager do?
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority . What should the risk manager do?A . Ask the project sponsor if every risk in the risk register...
What should the project manager do to evaluate and select the best option based on costs and probabilities?
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors. What should the project manager do to evaluate and select the best option based on costs and probabilities?A . Perform a FMECA fault tree analysisB...
What process is this part of?
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each...
When presenting their work to management, on what areas should the risk manager focus?
A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)A . Risks that are tied to the success of the organizationB . Risks as they apply...