Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed.
Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can infer that: A ....
In Agile projects, the technique in which planning is done at three distinct horizons is known as:
In Agile projects, the technique in which planning is done at three distinct horizons is known as:A . Monte Carlo Analysis.B . Portfolio Management.C . DelphiTechnique.D . Progressive Elaboration.View AnswerAnswer: D
A story point is the:
A story point is the:A . Relative measure of the size of a user story.B . Duration it takes to complete a user story.C . Priority of the user story in the backlog.D . Business value of the user story.View AnswerAnswer: A
Estimating costs for an Agile project starts with which of the following types of meetings?
Estimating costs for an Agile project starts with which of the following types of meetings?A . Project RetrospectiveB . Steering CommitteeC . Release PlanningD . Sprint PlanningView AnswerAnswer: C
When interacting with team members, the Agile project manager should:
When interacting with team members, the Agile project manager should:A . Ask team members to do things by phrasing the statement as a request rather than as a demand.B . Ignore team member input and emotions when important decisions have to be made.C . Proceed cautiously when requesting team members...
After three iterations, the problems impeding an Agile team appear to be similar in nature to problems faced in earlier iterations. Inspection of the retrospectives for past iterations reveals information organized into columns entitled “What worked for us” and “What did not work for us. ” Based on this information, one can infer that the team did not capture:
After three iterations, the problems impeding an Agile team appear to be similar in nature to problems faced in earlier iterations. Inspection of the retrospectives for past iterations reveals information organized into columns entitled “What worked for us” and “What did not work for us. ” Based on this information,...
At a strategic level, what is the most appropriate way for an Agile team to estimate a project?
At a strategic level, what is the most appropriate way for an Agile team to estimate a project?A . Creating a strategic plan by estimating hours and days requiredB . Using an abstract measurement to estimate Product Backlog itemsC . Estimating source lines of code needed to implement the featuresD...
What is the responsibility of an extreme Programming (XP) customer role?
What is the responsibility of an extreme Programming (XP) customer role?A . Testing the daily increments of the software developedB . Writing the stories and acceptance tests for each storyC . Planning and task allocation for the developer and testerD . Interacting closely with users and representing the XP teamView...
Which of the following best describes a core belief of Agile?
Which of the following best describes a core belief of Agile?A . The best customer feedback comes near the end of the project when there is working software to review.B . Project status can be gauged by frequently reviewing completed milestones as reflected in the plan.C . Working solutions are...
What key benefits might stakeholders realize from an Agile approach?
What key benefits might stakeholders realize from an Agile approach?A . The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet dailyB . The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustmentsC...