A “Scrum of Scrums” meeting is:
A “Scrum of Scrums” meeting is:A . Another name for the daily standup project meeting in a Scrum team.B . A mechanism that coordinates multiple teams working on a single project.C . A project meeting that happens twice every day across the Scrum teams.D . An occasional leadership meeting that...
Who is responsible for determining the business value of each feature?
Who is responsible for determining the business value of each feature?A . Product OwnerB . Steering committeeC . ScrumMasterD . TeamView AnswerAnswer: A
Agile project development processes typically:
Agile project development processes typically:A . Encapsulate analysis, design, code, and test within an iteration.B . Document each business process individually and in detail.C . Use a Gantt chart with well-defined activities, responsibilities, and time frames.D . Map the iteration backlog to a Work Breakdown Structure (WBS).View AnswerAnswer: A
A user story says that a product must be very fast. During the demo, the Product Owner is dissatisfied with the speed of the product.
A user story says that a product must be very fast. During the demo, the Product Owner is dissatisfied with the speed of the product. The most likely reason that this occurred is because the user story was:A . Too large.B . Not estimated correctly.C . Not testable.D . Not...
Risk exposure is the:
Risk exposure is the:A . Funds set aside to contain the risk.B . Probability a risk will occur.C . Amount of money the risk will cost if it occurs.D . Amount of damage to the project if the risk occurs.View AnswerAnswer: C
Which of the following is an example of a visual aid used in Lean-Agile software development?
Which of the following is an example of a visual aid used in Lean-Agile software development?A . Business value delivered chartB . Product technical specificationsC . Automated code coverage reportD . Scrum-of-Scrum reportView AnswerAnswer: A
Which tool allows the Product Owner to focus on providing the greatest value and Return on Investment (ROI) to the organization?
Which tool allows the Product Owner to focus on providing the greatest value and Return on Investment (ROI) to the organization?A . Burn up chartB . Product BacklogC . Affinity estimateD . Cost Benefit Analysis (CBA)View AnswerAnswer: B
When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take?
When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take?A . Stop work on unfinished user stories and work on the urgent request.B . Call a team meeting and change the iteration scope to include...
Which are some of the most important benefits of an Agile team sitting together in a co-located, open environment?
Which are some of the most important benefits of an Agile team sitting together in a co-located, open environment?A . Osmotic communication is reduced; space is used more efficiently; groups work together more effectively, and team dynamics are improved.B . Costs are reduced as the need for conference rooms decreases,...
Which of the following drivers is the most important factor in determining the order in which stories will be developed?
Which of the following drivers is the most important factor in determining the order in which stories will be developed?A . Relative costB . Customer valueC . Development effortD . DependenciesView AnswerAnswer: B