In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?
In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?A . Release planningB . Sprint planningC . Sprint RetrospectiveD . Daily ScrumView AnswerAnswer: C
On a particular project, product quality is being measured at regular intervals and is consistently below the acceptable level. In a Lean environment, how should this problem be addressed?
On a particular project, product quality is being measured at regular intervals and is consistently below the acceptable level. In a Lean environment, how should this problem be addressed?A . The team should implement more rigorous testing at the end of each development cycle.B . Management should direct the team...
The term “last responsible moment” refers to the moment at which:
The term “last responsible moment” refers to the moment at which:A . the iteration testing deadline arrives and code testing must stop.B . failing to make a decision eliminates an important alternative.C . release planning is complete and the first iteration planning starts.D . the implementation date is set and...
What is the best first step the business analyst should take regarding this risk?
A business analyst has identified a new risk in an Agile project. What is the best first step the business analyst should take regarding this risk?A . Call a meeting with the project manager and senior management to determine how the risk will be managed.B . Email the project manager...
Team A is producing 61 points per iteration and Team B is producing 20 points per iteration. Team A has more senior engineers. A manager demands that Team B match Team A’s points in the next iteration.
Team A is producing 61 points per iteration and Team B is producing 20 points per iteration. Team A has more senior engineers. A manager demands that Team B match Team A’s points in the next iteration. Based on this information, it is reasonable to tell the manager that: A....
A value stream map is a tool used to identify the:
A value stream map is a tool used to identify the:A . Waste across the entire process.B . Highest value product features.C . Most valuable team interactions.D . Most likely flow of project risks.View AnswerAnswer: A
Continuous integration ensures that a product is:
Continuous integration ensures that a product is:A . Ready to ship when all features are complete.B . Delivered for testing at the end of each day.C . Technologically ready to deploy at any time.D . Deployed after final business approvals.View AnswerAnswer: C
Who is responsible for making sure that each user story is associated with at least one user role or persona?
Who is responsible for making sure that each user story is associated with at least one user role or persona?A . UserB . DeveloperC . CustomerD . PersonaView AnswerAnswer: C
Refactoring, as it applies to the practice of extreme Programming (XP), refers to:
Refactoring, as it applies to the practice of extreme Programming (XP), refers to:A . Restructuring the estimate by applying a higher cost performance index during ¡°what if¡± analysis.B . Modifying the project due to scope changes, resource availability, and cost and schedule variances.C . Modifying the cost baseline due to...
Project managers use velocity to determine: