During stakeholder engagement planning, the program manager should consider which of the following stakeholders aspects?

A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning, the program manager should consider which of the following stakeholders aspects?A . Attitude about the program, external political position, and...

June 22, 2021 No Comments READ MORE +

What should be done with the identified potential risk?

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention. What should be done with the identified potential risk?A . Incorporate it into the risk register and perform a thorough analysis.B ....

June 22, 2021 No Comments READ MORE +

Which project should the program manager select to be cancelled?

A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment . The program manager has the following information to guide and support the decision: Which project should the program manager select to be...

June 21, 2021 No Comments READ MORE +

When a project in your program is completed, who will need to sign the certificate of completion?

You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion?A . The project managerB . The program customerC . The program stakeholdersD . The project management teamView AnswerAnswer: B

June 21, 2021 No Comments READ MORE +

Which one of the following is the best chart for Gina in this situation?

Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of...

June 21, 2021 No Comments READ MORE +

Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?

You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are...

June 21, 2021 No Comments READ MORE +

The program manager should verify alignment with which of the following?

The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?A . Program charterB . Organizational structures and policiesC . Organizational strategic objectivesD . Program governance planView AnswerAnswer: C

June 21, 2021 No Comments READ MORE +

Which of the following processes are you on?

You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?A . Report Program PerformanceB . Monitor and...

June 21, 2021 No Comments READ MORE +

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?A . .99B . -$2,500C . $2,500D . 1.02View AnswerAnswer: C

June 20, 2021 No Comments READ MORE +

Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how...

June 20, 2021 No Comments READ MORE +