Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?
You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are...
When will the program team be acquired for a program?
You are the program manager for your organization. Part of your role as the program manager is to train John, a new program manager, on the program processes within a program. John is confused as to when the program team can be acquired in the program management lifecycle. When will...
Which is the only technique (or tool) available in the Close Project or Phase process?
You are the project manager of a construction project. You have to close a phase of the project. Which is the only technique (or tool) available in the Close Project or Phase process?A . Change control meetingsB . Project management information systemC . Expert judgmentD . ObservationsView AnswerAnswer: C
Which one of the following is an output of the communications control process?
You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?A . Approved change requestsB . Communications management planC . Stakeholder analysis chartsD...
During program execution, how does a program manager ensure that benefits are being realized in accordance with program governance?
During program execution, how does a program manager ensure that benefits are being realized in accordance with program governance?A . By reviewing the benefits management planB . By updating the benefits registerC . By conducting benefits analysis and planningD . By reviewing the program business caseView AnswerAnswer: B Reference: https://www.pmi.org/-/media/pmi/documents/public/pdf/learning/thought-leadership/benefits-...
How should the program manager decide which template is appropriate?
Component project managers create project management plans for all component projects in a program . The program manager notices that some project managers prefer one status report template, while others prefer another. How should the program manager decide which template is appropriate?A . Review the issue with the program management...
All of the following information is defined in the program statement of work except for which one?
You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?A . Program requirements for resource competency levelsB . Structure of...
What does CPI value less than 1.0 indicates?
What does CPI value less than 1.0 indicates?A . Cost overrun for work completedB . Scheduled performance is greatC . Cost underrun of performance to dateD . Cost for completed work is as per estimateView AnswerAnswer: A
What is this phenomenon called?
You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart. What is this phenomenon called?A . Rule of ImprovementB . Mean ImprovementC . Rule of...
The program manager should verify alignment with which of the following?
The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?A . Program charterB . Organizational structures and policiesC . Organizational strategic objectivesD . Program governance planView AnswerAnswer: C