The outsourcing of the dangerous work to a specialist is what type of risk response?
You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work...
When a project in your program is completed, who will need to sign the certificate of completion?
You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion?A . The project managerB . The program customerC . The program stakeholdersD . The project management teamView AnswerAnswer: B
Which earned value management formula can help you determine how likely it is that you'll complete the program based on the amount of cash left in the program budget?
Which earned value management formula can help you determine how likely it is that you'll complete the program based on the amount of cash left in the program budget?A . Estimate at completionB . Variance at completionC . To-complete performance indexD . Estimate to completeView AnswerAnswer: C
Taking which of the following steps could have been prevented the situation?
Martha is sharing her experience of her last project as the project manager. She tells that when she presented customer a formal acceptance and sign-off document, they refused to sign, claiming that the product does not meet their expectation. Taking which of the following steps could have been prevented the...
What should the regional program manager do to address the country manager’s request?
A newly appointed country manager suggests that the regional program manager use a social media platform to expedite communications and address questions. The new country manager used this social media platform at a previous job. What should the regional program manager do to address the country manager’s request?A . Suggest...
What document asks the seller to provide your project with a detailed description of a project solution along with a price to complete the project work?
What document asks the seller to provide your project with a detailed description of a project solution along with a price to complete the project work?A . ProposalB . RFPC . BidD . QuoteView AnswerAnswer: A
What duration compression technique should Kelly use in this instance?
Kelly's program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They've asked Kelly to use a schedule duration compression technique that will help the program finish on time . The technique...
Which one of the following is the best chart for Gina in this situation?
Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of...
What should the program manager do next?
A component project of a multiyear program delivers all expected products and services as anticipated . The component project manager obtains approvals from the stakeholders and transitions the benefits to operations. What should the program manager do next?A . Reassign the component project manager to another component project or activityB...
Where are negative risks recorded?
Where are negative risks recorded?A . Negative risk registerB . Risk management planC . Risk registerD . Issues logView AnswerAnswer: C