Enterprise environmental factors are an input to which process?
Enterprise environmental factors are an input to which process?A . Control Scope B. Define Scope C. Plan Scope Management D. Collect RequirementsView AnswerAnswer: C
Which process determines the risks that may affect the project and documents their characteristics?
Which process determines the risks that may affect the project and documents their characteristics?A . Control Risks B. Plan Risk Management C. Plan Risk Responses D. Identify RisksView AnswerAnswer: D
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?A . External B. Internal C. Mandatory D. DiscretionaryView AnswerAnswer: D
The process of prioritizing risks for further analysis or action is known as:
The process of prioritizing risks for further analysis or action is known as:A . Plan Risk Management. B. Plan Risk Responses. C. Perform Qualitative Risk Analysis. D. Perform Quantitative Risk Analysis.View AnswerAnswer: C
An input to the Identify Stakeholders process is:
An input to the Identify Stakeholders process is:A . The project management plan. B. The stakeholder register. C. Procurement documents. D. Stakeholder analysis.View AnswerAnswer: C
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?A . Organizational process updates B. Quality metrics C. Change requests D. Quality control measurementsView AnswerAnswer: B
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:A . Customers. B. Business partners. C. Sellers. D. Functional managers.View AnswerAnswer: B
An input to Conduct Procurements is:
An input to Conduct Procurements is:A . Independent estimates. B. Selected sellers. C. Seller proposals. D. Resource calendars.View AnswerAnswer: C
Which document describes the necessary information to determine if a project is worth the required investment?
Which document describes the necessary information to determine if a project is worth the required investment?A . Cost baseline B. Service level agreement C. Memorandum of understanding D. Business caseView AnswerAnswer: D
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?A . Project document updates B. Activity list C. Activity attributes D. Project calendarsView AnswerAnswer: C