The process of identifying and documenting relationships among the project activities is known as:

The process of identifying and documenting relationships among the project activities is known as:A . Control Schedule. B. Sequence Activities. C. Define Activities. D. Develop Schedule.View AnswerAnswer: B

January 25, 2023 No Comments READ MORE +

A regression line is used to estimate:

A regression line is used to estimate:A . Whether or not a process is stable or has predictable performance. B. How a change to the independent variable influences the value of the dependent variable. C. The upper and lower specification limits on a control chart. D. The central tendency, dispersion,...

January 25, 2023 No Comments READ MORE +

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?A . Interrelationship digraphs B. Tree diagram C. Affinity diagram D. Network diagramView AnswerAnswer: B

January 25, 2023 No Comments READ MORE +

A temporary endeavor that creates a unique product or service is called a:

A temporary endeavor that creates a unique product or service is called a:A . Project B. Plan C. Program D. PortfolioView AnswerAnswer: A

January 25, 2023 No Comments READ MORE +

Which cost is associated with nonconformance?

Which cost is associated with nonconformance?A . Liabilities B. Inspections C. Training D. EquipmentView AnswerAnswer: A

January 25, 2023 No Comments READ MORE +

The number of potential communication channels for a project with 5 stakeholders is:

The number of potential communication channels for a project with 5 stakeholders is:A . 10. B. 12. C. 20. D. 24.View AnswerAnswer: A

January 24, 2023 No Comments READ MORE +

When should quality planning be performed?

When should quality planning be performed?A . While developing the project charter B. In parallel with the other planning processes C. As part of a detailed risk analysis D. As a separate step from the other planning processesView AnswerAnswer: B

January 24, 2023 No Comments READ MORE +

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:A . Earned value management. B. Enterprise environmental factors. C. Organizational process assets. D. Work performance information.View AnswerAnswer: D

January 24, 2023 No Comments READ MORE +

Which process numerically analyzes the effect of identified risks on overall project objectives?

Which process numerically analyzes the effect of identified risks on overall project objectives?A . Plan Risk Management B. Plan Risk Responses C. Perform Quantitative Risk Analysis D. Perform Qualitative Risk AnalysisView AnswerAnswer: C

January 24, 2023 No Comments READ MORE +

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?A . Plan Procurement Management B. Control Procurements C. Collect Requirements D. Plan Cost ManagementView AnswerAnswer: A

January 24, 2023 No Comments READ MORE +