An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.
What should the risk management team leader do in the early stages of the project?
- A . Conduct qualitative risk analysis to prioritize potential risks.
- B . Plan a solid risk response plan and secure the necessary funding.
- C . Educate stakeholders on best practices to perform risk management.
- D . Benchmark to an organization which has executed a similar project,
A project manager is assigned to a new project and is told they need to develop the project’s risk register.
When should the project manager identify the project risks?
- A . Identify risks only at the project’s midpoint for the stakeholders to review them
- B . Ensure project team members proactively identify risks throughout the project to plan for possible response strategies
- C . Identify risks at the beginning of the project because the risk posture will not change
- D . Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas
A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?
- A . Review potential next steps with the project team.
- B . Review the scope of work to determine the prescribed project methodology.
- C . Review the policies and practices that are outlined in the risk management plan.
- D . Review the contract and determine the resources and project funding.
A risk manager faces resistance as they try to implement the project’s risk strategy. Some members of the project team believe it is a waste of time and money.
What should the risk manager do?
- A . Continue to implement the risk strategy
- B . Meet with team members to address their concerns.
- C . Reduce the number of risk management activities.
- D . Raise the concerns with the project sponsor,
A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process .
What should the risk manager do next with the data set?
- A . Perform a probability and impact assessment
- B . Perform Monte Carlo simulations
- C . Perform a sensitivity analysis
- D . Perform a risk data quality assessment
The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently .
What should the project manager do regarding those risks?
- A . Review the assumptions analysts
- B . Conduct a checklist analysis on each risk
- C . Create a risk response plan for those risks
- D . Review the risk register to check for the new risks
A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS 1. 5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1. 2 and cost performance index (CPI) is 0.53 .
How should the risk manager interpret such a low CPI value?
- A . The cost control processes is ineffective.
- B . The cost baseline is inaccurate.
- C . The actual reported costs are inaccurate.
- D . The cost related risks are effectively managed.
A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.
What should the risk manager do with this risk?
- A . Put the risk on the watch list.
- B . Seek guidance from subject matter experts (SMEs).
- C . Ignore this risk as it is not critical.
- D . Inform the stakeholders about this risk.
A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.
What should the project manager do to avoid this risk?
- A . Record this risk and the clients preference in the risk register.
- B . Ask the sales person to lead the communication with the client
- C . Call the client and advise that online communication is easier and faster.
- D . Meet the client and plan tor critical milestone meetings.
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.
Which document will need to be updated?
- A . Lessons learned
- B . Contingency register
- C . Risk register
- D . Issue log