PMI PMI-RMP PMI Risk Management Professional Online Training
PMI PMI-RMP Online Training
The questions for PMI-RMP were last updated at Apr 16,2025.
- Exam Code: PMI-RMP
- Exam Name: PMI Risk Management Professional
- Certification Provider: PMI
- Latest update: Apr 16,2025
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established .
How should the risk manager proceed?
- A . Perform a qualitative risk analysis and update the results.
- B . Update the assumptions/exclusions register with the new information.
- C . Update the risk register and prepare for the Monte Carlo analysis.
- D . Perform a quantitative risk analysis and update the results.
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG .
What should the project manager do first?
- A . Include the risk in the register and communicate with the stakeholders.
- B . Communicate with the client to provide the previous shutdown plan.
- C . Review and update the project schedule.
- D . Interview the other project manager to learn more details.
The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.
How should the project manager and the risk manager handle this situation?
- A . Ensure the project complies with the current traffic regulations and laws.
- B . Send a letter to the traffic authority with the general project information.
- C . Perform inquiries on the website of the traffic authority weekly.
- D . Meet with the traffic authority staff in charge of the new regulation.
A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks .
How should the project manager work with these risk handling strategies?
- A . Review and revise the strategies periodically.
- B . Implement the strategies after completing the risk analysis.
- C . Implement the strategies immediately.
- D . Ensure the strategies are approved by the stakeholders.
A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work .
What is the project manager performing in this situation?
- A . Risk mitigation
- B . Risk transfer
- C . Risk acceptance
- D . Risk avoidance
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing .
What should the risk manager do?
- A . Contact the risk managers of the other projects and inform them
- B . Include an escalation process in the risk management plan
- C . Take note of the extensive impact of these risks in the risk register
- D . Address the unique characteristics of these risks on a case-by-case basis
The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X’s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.
How should project X’s project manager avoid this situation in the future?
- A . Prepare a contingency response plan to implement when delays occur
- B . Ask the other project manager to officially confirm the new date in writing
- C . Request that the other project manager be added to relevant reports
- D . Request that the other project manager inform if any additional delays are expected
An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats .
What should the risk manager do next?
- A . Add only the threats to the risk register
- B . Utilize different tools to identify the risks
- C . Plan risk responses to the threats
- D . Update the risk register with the identified risks
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?
- A . Implement the risk response strategies into the risk plan.
- B . Inform the sponsor that these risks should be added according to experience.
- C . Add the risks to the risk register and determine a contingency.
- D . Discuss and evaluate the identified risks with the project team.
During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.
What should the risk manager do to handle this situation?
- A . Revisit this risk in the risk register and redefine the mitigation strategy.
- B . Activate the contingency plan to handle this risk during execution.
- C . Mark this new risk as an extremely high priority and inform all stakeholders.
- D . Ask the project sponsor for more budget to deal with this risk.