PMI PMI-RMP PMI Risk Management Professional Online Training
PMI PMI-RMP Online Training
The questions for PMI-RMP were last updated at Apr 21,2025.
- Exam Code: PMI-RMP
- Exam Name: PMI Risk Management Professional
- Certification Provider: PMI
- Latest update: Apr 21,2025
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin. The project manager would like the risk manager to take full advantage of opportunities.
Which response should the risk manager take?
- A . Mitigate
- B . Accept
- C . Transfer
- D . Exploit
The project manager performed’ a variance analysis on the project during the execution phase. The
variances were shown as increasing
What does this result imply?
- A . The uncertainty and risk are increasing.
- B . The project schedule is lagging behind.
- C . There is no potential for future deviation.
- D . The project is over budget.
The risk manager conducted an updated Monte Carlo simulation for the project at the end of a phase. The simulation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?
- A . Add more float to the key activity
- B . Add more contingency to the project
- C . Review the plans for the key activity
- D . Increase the budget for the key activity
A project that was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.
What three artifacts should the project manager consult or review during this process? (Choose three.)
- A . Project contracts
- B . Lessons learned registers from analogous projects
- C . Risk register
- D . Risk management plan
- E . Code of regulations
A risk manager of a major project facilitates a meeting to develop the risk management plan .
What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)
- A . Applying modern risk management techniques.
- B . Aligning to project constraints and priorities.
- C . Ensuring risk response strategies mitigate all risks.
- D . Minimizing implementation costs.
- E . Obtaining stakeholder acceptance
Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others .
What should the project manager do?
- A . Reduce the probabilities of those risks on the risk register
- B . Transfer ownership of those risks to the customer
- C . Implement the risk handling strategies for those risks
- D . Request additional management reserve for those risks
A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss .
What is the expected monetary value for this project?
- A . US$20.000 loss
- B . US$20,000 profit
- C . US$40,000 loss
- D . US$100,000 profit
The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder .
What should the project risk manager do next to identify risks?
- A . Review the risk breakdown structure to ensure project scope is covered.
- B . Use the brainstorming technique to remove personal bias.
- C . Use expert judgment to remove ego or emotional conflict.
- D . Consider the Delphi technique to gather all stakeholder opinions.
A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization’s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges.
What two actions should the risk owner take? (Choose two.)
- A . Implement the secondary risk response and update the project documents.
- B . Conduct meeting with all stakeholder to agree on post impact solutions.
- C . Set the corresponding trigger conditions to the secondary risk.
- D . Engage the project manager to authorize the secondary risk’s response.
- E . Update and communicate assessments of the secondary risk’s impact.
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.
What should the project manager do next?
- A . Review assumptions and constraints around risks.
- B . Develop the risk response plans for identified risks.
- C . Determine the likelihood and impact of the risks.
- D . Apply an iterative approach to risk identification.