PMI PMI-RMP PMI Risk Management Professional Online Training
PMI PMI-RMP Online Training
The questions for PMI-RMP were last updated at Feb 24,2025.
- Exam Code: PMI-RMP
- Exam Name: PMI Risk Management Professional
- Certification Provider: PMI
- Latest update: Feb 24,2025
The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway .
What should the project manager do?
- A . Wait until the weather improves before sending the equipment.
- B . Ask the project sponsor to approve shipping the equipment.
- C . Proceed with the planned risk response to move the equipment.
- D . Request the shipment of the equipment to satisfy the client.
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?
- A . Add buffers to the schedule to accommodate risk.
- B . Ensure the risk register includes all identified risks.
- C . Discuss the risk response strategies with the stakeholders.
- D . Develop a communication plan to share updates on risks.
A company in the mining industry accommodates a lot of innovation and changing work conditions.
Because of this, the company experiences difficulty in predicting long term business plans.
How should a professional risk manager manage the risks in such situations?
- A . Adopt a predictive approach to manage the risks.
- B . Adopt agile approaches to manage the risks.
- C . Utilize proper documentation to help manage the risks.
- D . Conduct weekly risk management meetings with all stakeholders.
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations .
What should the project manager do next?
- A . Identify secondary or residual risks for associated risk plans.
- B . Develop risk response plans for all identified risks.
- C . Update the communications management plan to avoid future issues
- D . Monitor and control secondary and residual risks in the risk register.
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
- A . Provided regular training to the risk owners for plan implementation
- B . Determined risk triggers and thresholds in the risk response plan
- C . Increased communications to influence stakeholder risk responses
- D . Updated the project schedule, adding risk owner implementation tasks.
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
- A . Plan Risk Management
- B . Perform Qualitative Risk Analysis
- C . Perform Quantitative Risk Analysis
- D . Monitor and Control Risk
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors .
What should the project manager do when engaging stakeholders?
- A . Include all stakeholders in the project’s governance.
- B . Communicate response strategies to all stakeholders.
- C . Ignore any risks beyond stakeholders’ tolerance.
- D . Consider stakeholders’ positions and opinions regarding the project’s output.
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?
- A . Check list analysis
- B . Cause and effect
- C . Specialized meeting
- D . Quantitative analysis
Project stakeholders can often be risk averse with little to no knowledge of the risk process .
How should a risk manager increase stakeholder risk appetite?
- A . Exclude risk averse stakeholders from future risk discussions
- B . Explain risk handling and mitigation strategies
- C . Increase the impact of all risks in the risk breakdown structure (RBS)
- D . Develop a generous probabilistic cash flow model
A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described .
What is critical for the risk manager to consider when describing the causes?
- A . Each cause has a degree of uncertainty
- B . Each cause has well defined owner
- C . The causes represent actual conditions
- D . The causes must be validated by the risk owner