PMI PMI-RMP PMI Risk Management Professional Online Training
PMI PMI-RMP Online Training
The questions for PMI-RMP were last updated at Feb 24,2025.
- Exam Code: PMI-RMP
- Exam Name: PMI Risk Management Professional
- Certification Provider: PMI
- Latest update: Feb 24,2025
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
What should the risk management professional do next?
- A . Perform a sensitivity analysis to the higher-level aggregate activities
- B . Develop a risk breakdown structure (RBS) identifying the potential risk categories
- C . Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis
- D . Perform a base line Monte Carlo simulation to address overall threats to project objectives
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment.
What should the risk manager do?
- A . Confirm the risk triggers are still valid.
- B . Ask the architect to develop acceptance criteria.
- C . Review the feature with the project team.
- D . Escalate the issue to the project board.
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority .
What should the risk manager do?
- A . Ask the project sponsor if every risk in the risk register can have the same priority.
- B . Mark every identified risk as an extremely high priority and any future risks as a lower priority.
- C . Agree with the SME, treat every risk with equal priority, and inform all stakeholders.
- D . Perform a sensitivity analysis and determine the correct priority of every identified risk.
The risk manager notices that in their workshops, most of the risks identified are threats .
What should the risk manager do to increase the number of opportunities identified?
- A . Use the Delphi technique involving experts who have identified opportunities in the past
- B . Interview more stakeholders who have a positive mindset
- C . Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis
- D . Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis
During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting .
What should the project manager do?
- A . Utilize a Monte Carlo assessment to provide risk related impacts.
- B . React to the secondary and residual risks only if they occur.
- C . Include secondary and residual risks as part of the response.
- D . Transfer secondary and residual risks to the project sponsor.
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
- A . Industrial studies
- B . Commercial risk databases
- C . Organizational process assets (OPAs)
- D . Enterprise environmental factors (EEFs)
A risk manager is confident that they have identified and quantified the risks and opportunities for a project.
When presenting their work to management, on what areas should the risk manager focus? (Choose two.)
- A . Risks that are tied to the success of the organization
- B . Risks as they apply to the organization’s overall risk management philosophy and strategic ambition
- C . Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year
- D . Risks related to cost that will impact the major projects that are currently in the execution phase
- E . Risk mitigation actions that will require work from stakeholders
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option’s success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?
- A . Perform a FMECA fault tree analysis
- B . Conduct a sensitivity analysis
- C . Perform a decision tree analysis
- D . Conduct an analytic hierarchy process
When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project’s contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.
What should the project manager do?
- A . Process the freight invoices at higher shipping costs against the project’s contingency allowance.
- B . Request a formal change order from the customer to increase the project’s total budget.
- C . Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.
- D . Ask the project sponsor to cover the additional shipping costs on the company’s reserves account.
A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company’s business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds .
What should the project manager do next?
- A . Update the project management plan to add contingency.
- B . Perform an assumptions and constraints analysis.
- C . Complete an assessment and confirm the response with the sponsors.
- D . Implement mitigation measures for those risks.